background image

8

FURNACE SIZING AND DUCT SYSTEM
DESIGN

The duct system must be installed in conformance
with ASHRAE/NFPA 90, Standard for Installation of
Warm Air Heating and Air Systems and other
applicable local codes. Failure to adhere to proper
duct system design standards can reduce airflow,
resulting in reduced system performance and
possible furnace damage.

Consideration should be given to the heating
capacity required and also to the air quantity (CFM)
required if A/C is to be installed along with the
furnace or at some future time. These factors can be
determined by calculating the heat loss and heat
gain of the home or structure.

If these calculations are not performed and the
furnace is oversized, the following may result:

1.  Short cycling of the furnace.

2.  Wide temperature fluctuations from the thermo-

stat setting.

3.  Reduced overall operating efficiency of the

furnace.

The supply and return duct system must be of
adequate size and designed such that the furnace
will operate within the designed air temperature rise
range and not exceed the maximum designed static
pressure. These values are listed in the table below.

EXT. STATIC IN. W.C.

INPUT BTUH

MINIMUM

MAXIMUM

50,000

.10

.50

75,000

.12

.50

100,000

.15

.50

125,000

.20

.50

Additional information, values and data necessary
for heat loss, heat gain and duct system design may
be found in the ASHRAE HANDBOOK OF FUNDA-
MENTALS or in other nationally recognized publica-
tions recognized by municipal, state, provincial and
federal code authorities.

If possible, it is recommended that the supply air
duct attached to the furnace be provided with a
removable access panel. The opening should be
accessible when the furnace is installed in service
and should be large enough that smoke or reflected
light may be observed inside the casing to indicate
the presence of leaks in the heat exchanger. The
cover panel for this opening should be attached in
such a manner as to prevent leaks.

A/C Usage Duct Systems

1.  When a single (common) duct system is used,

one of the following methods shall be used:
a.  A plenum type cooling coil must be installed

on the air discharge side, or

b.  A blower-coil type cooling coil must be in-

stalled in parallel with and isolated from the
furnace, or

c.  A self-contained A/C unit must be in parallel

with and isolated from the furnace.

Dampers must be installed when coil-blower
or self-contained unit is employed to pre-
vent conditioned cool air from coming in
contact with the heat exchanger to avoid
moisture condensation and rust-out. This
can allow products of combustion to be cir-
culated into the living area by the furnace
blower resulting in possible asphyxiation. If
dampers are of a manually operated type, a
means must be provided to prevent either
the furnace or A/C unit from operating un-
less dampers are in full heat or cool posi-
tion.

If two duct systems are used as could be the case
with a coil-blower or a self-contained A/C unit, the
furnace and A/C unit should be controlled by a
single combination heating and cooling thermostat
which will prevent the furnace and A/C unit from
operating simultaneously.

If a separate heating and separate cooling
thermostat is used, a manually operated
electrical interlock switch must be installed
to prevent simultaneous operation of both
systems and to avoid a possible hazardous
condition due to overheating of the condi-
tioned space.

RETURN AIR AND FILTERS

Return Air Temperature

This furnace design is to be operated in normal
household temperatures. The continuous return air
temperature must not be below 60°F or above 85°F.

Return Air Connection – Upflow

The return air may be brought in through the bottom
of the furnace or through one or both sides of the
furnace casing. The furnace casing may be cut out
so that side return air connections may be used. The
furnace is supplied with flanges on the top of the
furnace to which the return air duct may be fastened.
The casing top is embossed to indicate where to
bend the flanges. If a side return is to be used, cut
out the side of the casing 14" high by 16 1/4" wide
using the lances in the casing side as a guide. DO
NOT CUT THE OPENING LARGER THAN 14"x 16
1/4".
 It is not permissible to cut out the back of the
furnace.

Summary of Contents for G8C 50

Page 1: ...RATION 18 FURNACE OPERATION 18 INSTALLATION CHECKS 19 SERVICE INSTRUCTIONS 21 REPLACEMENT PARTS 21 GENERAL INFORMATION These instructions are for the use of qualified individual specially trained and experienced in installation of this type equipment and related system components Installation and service personnel are required by some states to be licensed Persons not qualified shall not install t...

Page 2: ...5521 100 000 21 10 x 10 40 70 1600 170 1 2 4 2804 5521 100 000 24 1 2 2 10 x 6 35 65 2000 165 3 4 4 2805 5521 125 000 24 1 2 2 10 x 6 40 70 2000 170 3 4 5 2805 5521 All models are supplied with 3 vent connections An installer supplied transition to 4 or 5 diameter must be used where necessary A B C D E F G H J 17 1 2 21 24 1 2 16 1 2 20 23 1 2 20 3 8 20 3 8 20 3 8 20 20 20 16 19 1 2 23 14 1 2 18 2...

Page 3: ...staller must conform to all state local and provincial building codes when installing these appliances In the absence of state local or provin cial codes these furnaces and related equipment must be installed in accordance with the latest issue of the following NATIONAL FUEL GAS CODE ANSI Z223 1 NATIONAL ELECTRICAL CODE ANSI NFPA 70 Applicable codes take precedence over any recom mendation made in...

Page 4: ...crews 9 Rotate the vent blower and transition 180 so that its outlet points to the outlet air end of the furnaces as shown in Figure 2 10 Line up the vent blower mounting holes with the holes in the vent pan and screw it into place Use the same machine screws that held the vent blower in place previously 11 Install the two extra machine screws in the two open holes in the front of the vent pan See...

Page 5: ...ound knockout at the right side of the top cap See Figure 5 FIGURE 5 TOP CAP 16 Install the top cap at the opposite end of furnace from the vent blower using the seven sheet metal screws saved earlier See Figure 3 17 Install the bottom cap on the bottom of the furnace using the sheet metal screws saved earlier See Figure 3 18 The conversion is now complete The furnace may now be installed in the d...

Page 6: ...nstallations on Combustible Flooring This furnace may not be installed directly on com bustible materials in the downflow position It may be installed directly on floors made of concrete or other non combustible materials If it is necessary to install the furnace in the downflow position on a combusti ble floor it is required that a combustible sub base be used The part number of the correct sub b...

Page 7: ...UH of furnace input but not less than 100 square inches If all air is from outdoors when communicating directly with the outdoors through vertical ducts the total free area of each opening must be at least one square inch for each 4 000 BTUH of furnace input When communicating directly with the outdoors through horizontal ducts the total free area of each duct must be at least one square inch for ...

Page 8: ...of the following methods shall be used a A plenum type cooling coil must be installed on the air discharge side or b A blower coil type cooling coil must be in stalled in parallel with and isolated from the furnace or c A self contained A C unit must be in parallel with and isolated from the furnace Dampers must be installed when coil blower or self contained unit is employed to pre vent condition...

Page 9: ...ace casing for side return ducts The furnace is supplied with flanges on both ends of the furnace to which the supply and return air ducts may be fastened The casing is embossed on both ends to indicate where to bend the flanges The return air ducts to the furnace must have a total cross sectional area of not less than two square inches per 1000 BTUH of furnace input rating for heating operation I...

Page 10: ...ts concerning gas piping In the absence of local codes follow the recommen dations contained in NATIONAL FUEL GAS CODE ANSI Z223 1 for gas piping materials pipe sizing and the requirements for installation In Canada refer to the latest edition of the CAN CGA B149 Installation Code and local codes for specifics It is recommended that a gas cock shutoff valve be installed in the gas supply line outs...

Page 11: ...11 FIGURE 9 DOWNFLOW CONFIGURATION FIGURE 10 UPFLOW CONFIGURATION ...

Page 12: ...wall venting beginning on page 16 The vent installation shall be in accordance with Part 7 Venting of Equipment of the NATIONAL FUEL GAS CODE ANSI Z223 1 or applicable provisions of the local building codes In Canada for more information regarding vent design and installation refer to the latest edition of the CAN CGA B149 Installation Code 1 This furnace must be connected to a factory built chimn...

Page 13: ...ication it must be rebuilt to conform to nationally recognized standards lined or relined with a suitable liner or replaced with a suitable vent or chimney Venting with Metal Pipe Type B double wall vents must extend in a gener ally vertical direction with offsets exceeding 45 degrees except that one horizontal run may be allowed Any angle greater than 45 degrees from the vertical is considered ho...

Page 14: ...ter the old furnace is removed To test for an oversized vent system the following steps shall be followed with each appliance remaining con nected to the common venting system placed in operation while the other appliances remaining connected to the common venting system are not in operation 1 Seal any unused openings in the common venting system 2 Visually inspect the venting system for proper si...

Page 15: ... separate fused circuit from the main electrical panel should serve only the furnace Electrical Grounding The furnace casing must have an uninterrupted electrical ground in accordance with the National Electrical Code ANSI NFPA 70 or in Canada with the Canadian Electrical Code Part I and CSA C22 1 DO NOT use gas piping as an electrical ground Control Wiring The thermostat should be installed in ac...

Page 16: ...hould be connected to the terminals marked PARK on the blower control board in the furnace control box Motor Terminal Identification Four speed motors White Common Black High Blue Medium High Yellow Medium Low Red Low Three speed motors White Common Black High Blue Medium Red Low MOTOR SPEED TAP SELECTION FOR COOLING COOLING SYSTEM CAPACITY BTUH Furnace Input Blower Wheel 18 000 24 000 30 000 36 0...

Page 17: ...imit circuit Five flashes Rollout switch open Check for open rollout switches loose connections in rollout switch circuit Six flashes One hour pressure switch lockout Pressure switch has cycled four times in a single call for heat Check for vent blockage loose connec tions in pressure switch circuit Seven flashes One hour ignition lockout Burner failed to light in three tries Check gas flow gas pr...

Page 18: ...s present the system will monitor it and hold the gas valve open 6 If the burners fail to light within 6 8 seconds after the gas valve opens the gas valve will close and the ignitor will be turned off After a short pause the system will recycle and try again for ignition If the burners fail to light after three tries the ignition system will lock out The system will re main in lockout mode until o...

Page 19: ...on should also have a manual shutoff valve in the gas piping to the furnace similar to what is shown in Figure 14 To turn off the gas to the furnace use a wrench and turn the switch or lever so that it is pointing 90 degrees from the gas pipe as shown in Figure 14 FIGURE 14 MANUAL GAS SHUTOFF VALVE INSTALLATION CHECKS Checking Gas Input Rate Natural gas heating values can vary widely It is the res...

Page 20: ...rfired condition If it is determined that different orifices are needed please contact your distributor for assistance in selecting the correct replacement Minor Input Adjustment The input may be adjusted slightly by adjusting the pressure in the gas valve in order to change mani fold pressure To adjust pressure regulator remove cover screw See location on Figure 13 on valve Turn adjusting screw c...

Page 21: ...ace any component parts these may be obtained through an authorized dealer who is experienced and can be of assis tance Information on the nearest Distributor may be obtained directly from the company shown on the furnace rating plate Only genuine authorized replacement parts should be used Substitute parts should not be used as they may not be the same in opera tional and safety characteristics F...

Page 22: ...s 9 Ignitor 10 Transformer 11 Furnace Control 12 Pressure Switch 13 Gas Valve 14 Ignitor Bracket 15 Gas Orifice 16 Door Switch 17 Capacitor 18 Blower Wheel 19 Blower Motor 20 Sensor Rod 21 Blower Motor Clamp 22 Rubber Motor Mounts 23 Transition 24 Rollout Switch Bracket 25 Door Latch 26 Pressure Hose 27 Casing Bottom Cap Gasket Package not shown Wire Harness not shown ...

Page 23: ...23 ...

Page 24: ...Subject to change without notice Printed in U S A Copyright by Unitary Product Group 1998 All rights reserved 035 15815 401 9 98 P I Unitary Post Office Wichita Products Box 19014 KS Group 67204 24 ...

Reviews: