GAS PIPING INSTALLATION

Properly sized wrought iron, approved flexible or steel pipe must be
used when making gas connections to the unit. If local codes allow the
use of a flexible gas appliance connection, always use a new listed con-
nector. Do not use a connector that has previously serviced another gas
appliance.

Some utility companies or local codes require pipe sizes larger than the
minimum sizes listed in these instructions and in the codes. The furnace
rating plate and the instructions in this section specify the type of gas
approved for this furnace - only use those approved gases. The instal-
lation of a drip leg and ground union is required. Refer to Figure 4.

IMPORTANT: 

An accessible manual shutoff valve must be installed

upstream of the furnace gas controls and within 6 feet (1.8 m) of the fur-
nace.

The furnace must be isolated from the gas supply piping system by
closing its individual external manual shutoff valve during any pressure
testing of the gas supply piping system at pressures equal to or less
than 1/2 psig (3.5 kPa).

Gas piping may be connected from either side of the furnace using any
of the gas pipe entry knockouts on both sides of the furnace. Refer to
Figure 1 dimensions.

The inlet to the gas valve lines up directly with the opening in the left
side of the furnace casing. To line up with the opening in the right side
of the casing, two street ells should be used.

GAS ORIFICE CONVERSION FOR PROPANE (LP)

This furnace is constructed at the factory for natural gas-fired operation, 
but may be converted to operate on propane (LP) gas by using a fac-
tory-supplied LP conversion kit. Follow the instructions supplied with 
the LP kit. Refer to Table 6 or the instructions in the propane (LP) con-
version kit for the proper gas orifice size.

HIGH ALTITUDE GAS ORIFICE CONVERSION

This furnace is constructed at the factory for natural gas-fired operation
at 0 – 2,000 ft. (0 m – 610 m) above sea level.

The gas orifices on this furnace must be changed in order to maintain
proper and safe operation, when the furnace is installed in a location
where the altitude is greater than 2,000 ft. (610 m) above sea level on
natural gas or the altitude is greater than 4,000 ft. (1219 m) above sea
level on propane (LP) gas. Refer to Table 6 or the instructions in the
high altitude conversion kit for the proper gas orifice size.

The unit may also be converted for altitudes up to 10,000 ft. (3048 m)
on natural and propane (LP) gas with additional derate as shown in
Table 6 or refer to ANSI Z223.1 NFPA 54 National Fuel Gas Code or in
Canada CAN/CGA-B149.1-00 Natural Gas and Propane Installation
Code.

HIGH ALTITUDE PRESSURE SWITCH CONVERSION

For installation in locations where the altitude is less than 4,500 feet
(1372 m), it is not required that the pressure switch be changed, pro-
vided the maximum vent/intake pipe lengths are adjusted as shown in
the notes to Table 9. For altitudes above 4,500 feet (137 m), refer to
Instructions in the Accessory High Altitude Kit.

 FIGURE 4:  

Gas Piping

The gas valve body is a very thin casting that cannot take any
external pressure. Never apply a pipe wrench to the body of the gas
valve when installing piping. A wrench must be placed on the octa-
gon hub located on the gas inlet side of the valve. Placing a wrench
to the body of the gas valve will damage the valve causing improper
operation and/or the valve to leak.

EXTERNAL MANUAL
SHUTOFF VALVE

TO GAS
SUPPLY

TO GAS
SUPPLY

GROUNDED JOINT UNION
MAY BE INSTALLED
INSIDE OR OUTSIDE UNIT.

DRIP
LEG

TABLE 6: 

High Altitude Conversion

Type

Of Gas

Orifice at

Sea Level

2,000 ft.

(610 m)

3,000 ft.

(914 m)

4,000 ft.

(1219 m)

Natural

#45

#46

#47

#47

Propane

#55

#55

#55

#55

Type

Of Gas

5,000 ft.

(1524 m)

6,000 ft.

(1829 m)

7,000 ft.

(2134 m)

8,000 ft.

(2438 m)

Natural

#47

#48

#48

#49

Propane

#56

#56

#56

#56

Type

Of Gas

9,000 ft.

(2743 m)

10,000 ft.

(3048 m)

Natural

#49

#50

Propane

#56

#57

PROPANE AND HIGH ALTITUDE CONVERSION KITS
It is very important to choose the correct kit and/or gas orifices for
the altitude and the type of gas for which the furnace is being
installed.
Only use natural gas in furnaces designed for natural gas. Only use
propane (LP) gas for furnaces that have been properly converted to
use propane (LP) gas. Do not use this furnace with butane gas.
Incorrect gas orifices or a furnace that has been improperly con-
verted will create an extremely dangerous condition resulting in pre-
mature heat exchanger failure, excessive sooting, high levels of
carbon monoxide, personal injury, property damage, a fire hazard
and/or death.
High altitude and propane (LP) conversions are required in order
for the appliance to satisfactory meet the application.
An authorized distributor or dealer must make all gas conversions.
In Canada, a certified conversion station or other qualified agency,
using factory specified and/or approved parts, must perform the
conversion.
The installer must take every precaution to insure that the furnace
has been converted to the proper gas orifice size when the furnace
is installed. Do not attempt to drill out any orifices to obtain the
proper orifice size. Drilling out a gas orifice will cause misalignment
of the burner flames, causing premature heat exchanger burnout,
high levels of carbon monoxide, excessive sooting, a fire hazard,
personal injury, property damage and/or death.

Summary of Contents for PV9

Page 1: ...des TABLE OF CONTENTS SAFETY 1 DUCTWORK 3 FILTERS 6 GAS PIPING 6 ELECTRICAL POWER 8 COMBUSTION AIR AND VENT SYSTEM 9 CONDENSATE PIPING 16 SAFETY CONTROLS 16 START UP AND ADJUSTMENTS 17 WIRING DIAGRAM...

Page 2: ...tional vehicles Failure to carefully read and follow all instructions in this manual can result in furnace malfunction death personal injury and or property damage Furnaces for installation on combust...

Page 3: ...is required for passage to the front when servicing or for inspection or replacement of flue vent connections In all cases accessibility clearances shall take precedence over clear ances for combustib...

Page 4: ...ABLES 2 AND 3 are to be used as a guide only to help the installer determine if the duct sizes are large enough to obtain the proper air flow CFM through the furnace TABLES 2 and 3 ARE NOT to be used...

Page 5: ...rn End 5 Be sure to seal the furnace to plenum connections to prevent air leakage Refer to Figure 1 for unit and plenum dimensions Attic installations must meet all minimum clearances to combustibles...

Page 6: ...28 27 25 2000 57 C 16 x 25 41 x 64 20 x 25 51 x 64 120 112 2000 35 14 32 80 2000 57 D 2 16 x 25 2 41 x 64 22 x 25 56 x 64 All installations must have a filter installed Toe Plate Removable Rectangula...

Page 7: ...4 National Fuel Gas Code or in Canada CAN CGA B149 1 00 Natural Gas and Propane Installation Code HIGH ALTITUDE PRESSURE SWITCH CONVERSION For installation in locations where the altitude is less than...

Page 8: ...furnace s control system requires correct polarity of the power supply and a proper ground connection Refer to Figure 6 IMPORTANT The power connection leads and wiring box may be relo cated to the le...

Page 9: ...hese instructions IMPORTANT The VENT SYSTEM must be installed as specified in these instructions for Residential and Non HUD Modular Homes The sealed combustion air vent system is the only configurati...

Page 10: ...is as follows 1 Cut piping to the proper length beginning at the furnace 2 Deburr the piping inside and outside 3 Chamfer bevel the outer edges of the piping 4 Dry fit the vent piping assembly from th...

Page 11: ...1 US Installation2 A Clearance above grade veranda porch deck or balcony 12 inches 30 cm 12 inches 30 cm B Clearance to window or door that may be opened 6 inches 15 cm for applications 10 000 Btuh 3k...

Page 12: ...bustion air systems must be installed so the vent and the combustion air pipes terminate in the same atmospheric zone Refer to Figures 13 or 14 VENTING MULTIPLE UNITS Multiple units can be installed i...

Page 13: ...STION AIR Combustion air is supplied through a PVC or ABS pipe that is connected to the PVC coupling attached to the burner box and is terminated in a ventilated attic or crawl space The combustion ai...

Page 14: ...ion smaller than 0 25 6 4 mm 3 A manually operated damper or manually adjustable louvers are not permitted for use 4 A automatically operated damper or automatically adjustable lou vers shall be inter...

Page 15: ...w usage Follow all notes procedures and required materials in the SEALED COMBUS TION AIR SUPPLY section in these instructions when installing the combustion air pipe from the unit and into a ventilate...

Page 16: ...densate sump pump must be approved for use with acidic condensate CONDENSATE DRAIN TRAP AND DRAIN FREEZE PROTECTION Special precautions MUST be made if installing furnace in an area which may drop bel...

Page 17: ...bing 2 pieces of 4 10 cm length x 1 8 0 3 cm diameter tubing 1 5 16 0 8 cm tee 1 5 16 0 8 cm x 1 8 0 3 cm reducing coupling 1 1 8 0 3 cm adapter 1 Dwyer Manometer These items are required in order to...

Page 18: ...ivided by the time it took to measure 2 cubic ft 0 0566 m3 of gas from the gas meter For Propane LP Gas multiply the Heat content of the gas MJ m3 or Default 93 14 times 0 00283 m3 of gas measured at...

Page 19: ...as shown in Figure 24 The procedure below is used to adjust either the high fire manifold pressure or the low fire manifold pressure IMPORTANT The cap for the pressure regulator must be removed entir...

Page 20: ...Heating and Cooling Airflow The heating and the cooling airflows are preset at the factory The heat ing airflow is set to the maximum CFM The cooling airflow is set to pro vide 90 percent of the maxi...

Page 21: ...all for cooling the motor will ramp up to 63 of full capacity and will stay there for 90 seconds then will ramp up to full capacity At the end of the cooling cycle the motor will ramp down to 63 of fu...

Page 22: ...4 1880 1250 53 2 35 4 A C 1560 1010 44 2 28 6 1620 1030 45 9 29 2 C B 1470 940 41 6 26 6 1500 960 42 5 27 2 B C 1370 890 38 8 25 2 1410 880 39 9 24 9 D B 1460 930 41 3 26 3 1490 920 42 2 26 1 C A 125...

Page 23: ...the airflow table i e 0 20 w c 50 Pa 0 60 w c 150 Pa etc the system airflow cor responds to the intersection of the ESP column and Model Blower Speed row TABLE 16 Filter Performance Pressure Drop Inc...

Page 24: ...ed in U S A 035 20499 001 Rev B 1004 Copyright by York International Corp 2004 All rights reserved Supersedes 035 20499 001 Rev A 0904 Unitary 5005 Norman Product York OK Group Drive 73069 SECTION X W...

Reviews: