Operations Verification Check List
This checklist is designed to be a list of verifications after the
initial install has been completed Assuming all electrical and
tie in operations are complete and without issue
1�
Base Verification – Ensure the base of the unit is
supported in 1 of the 3 ways depicted in the Mounting
Options section If not, support properly before any
operation of the unit occurs
2�
Air balance verification - Your unit was sold to specific
parameters for CFM delivery at an ordered static
pressure (ESP) An air balance must be performed To
determine the total external static pressure, measure
using a manometer or magnehelic gauge Place the
negative side of the device into the return ductwork,
and the positive side into the supply ductwork The
supply must have a static pressure pitot tube to reduce
velocity pressure and must not be near the blower,
main plenum, or near 90°s, turning vanes, dampers or
duct reducers, ie anywhere turbulence can occur The
reading indicated on the device is the total ESP If the
unit is using an open mechanical room as the plenum,
the negative side may be placed in the room near the
filters, but the door to the mechanical room must be
closed You can then verify (on the controller status
screen) the RPM at which the unit is operating the VFD
drive Perform a duct traverse at the same time with an
anemometer (or similar device), with similar operating
parameters, to obtain the CFM
3�
Water balance verification – Ensure that the unit has
3 gpm per ton available to it at all times, if a pump is
of variable speed it must be able to ramp up its speed
based on that demand Variable Speed compressors
require a minimum of 12 hours of continuous crank
case heater energization before operation
Failure to
do so may result in liquid slugging on initial startup
which may cause damage to the compressor and will
void warranty To test the full water demand of the unit,
you must use the controller on the unit and apply a
manual control to the discharge pressure control valve
Visually inspect the valve to ensure it reads or points
to the OPEN position Also verify that the Water side
economizer valve is in the CLOSED position This
ensures that the valve is now requesting a full water
load scenario for the unit in mechanical cooling At
this time you may read the pressure drop across the
system and compare it to the unit’s submittal data Note
that each unit is built to custom specifications and you
will need data about your specific unit The pressure
drop data is an indicator of the heat exchangers
pressure drop, it does not include the piping which will
be marginal but will add additional resistance Note
that units may be ordered with multiple DPC valves
and other valves, in such case the design may require
some additional consideration before a water balance/
verification can be performed The entering water
temperature should not exceed 90°F and should not be
reduced to less than 50°F for best operating results If
equipped with a water side economizer the set point of
water side economizer operation should be verified