7
11. Turn on the laser system power switch.
Laser processing (engraving) can normally begin at this point.
See SECTION 3 - OPERATION for procedures for focusing laser beam and setting laser
controller parameters.
2.2.1 VETILATIO PROCEDURE
To properly exhaust fumes and smoke from the material surface during lasing, 400 cfm minimum
is required at the point of 4 inch connection to the system. Use maximum diameter rigid duct
work from the roof or down the wall. Reduce the duct work to four inches just before the point
of attachment to the laser system.
Locate laser system where a straight run to the ventilator can be achieved. Duct work should be
as short as possible between the ventilator and the laser system. Flexible ducting can be used
from the laser system to rigid duct work.
Ventilator should be equipped with an on/off switch and wired in accordance with local electrical
codes. We recommend plugging the laser system into a 110V switched outlet, controlled by the
on/off switch for the ventilator, to ensure laser system cannot be operated without the ventilator.
It is also advisable to power the laser system through a surge protector to prevent damage to the
electronics and laser.
Installation of the ventilation system should comply with all applicable local and government
regulations. We recommend the use of licensed contractors for installation of the equipment.
2.2.2 DIP SWITCH SETTIGS
There are two dip switch blocks on the main control board for the laser system and the cover
must be removed to access them. Each block contains ten switches and the two blocks are
referred to as Dip Switch one and two.
1.
Dip Switch 1 - Located on the right side of the system (under top enclosure) on the printed
circuit board with the parallel and serial interface connections. Dip Switch 1, marked
"DSW1", has 10 small switches, and is located next to parallel interface connection.
This switch is used to select the interface (parallel or serial), set field size, and character
font, etc. For details refer to "Dip Switch Setting Table" in Appendix A.
2.
Dip Switch 2 - Located on the right side of the system (under top enclosure) on the printed
circuit board with the parallel and serial interface connections. Dip Switch 2, marked
"DSW2", has 10 small switches, and is located next to Dip Switch 1.