___________________________________________________________________
United Renewable Energy Co., Ltd.
Page 33 of 45
Step 4
:
Turn off the GRID switch incl. external AC circuit breaker.
Step 5
:
If backup load is applied, turn off the Backup switch.
Step 6
:
Turn off the PV switch on the cable box and the external DC
breaker.
Step 7
:
Close the inner cover and outer shell of Cable box.
More information can be found in MA1-BAT user manual.