24
Zone 1
The leading edge of the gate & catch post.
Zone 2
Area between the gate and hinge post.
Zone 3
The arc of the gate or gate path.
Zone 4
The space between the gate when open and any obstruction such as fence, wall,
landscaping, etc.
Zone 5
The point where two bi-parting gates come together when closing. (Not shown below)
Every installation is unique and it is the installer’s responsibility to recognize and remedy all safety
concerns. Please consult a qualified dealer or the factory for a complete explanation of the remedies
shown above and additional tips pertaining to your installation.
All gate operators require periodic checking and adjustments of the control mechanism for force (load),
speed and sensitivity. All accessories and secondary safety devices must be checked. Secondary safety
devices need to be checked at least once a month for proper operation.
Periodic checking is also advised for the following:
1. Battery terminals for corrosion, clean with baking soda solution.
2. Hinges and pivot points need to be greased.
3. Mounting bolts for correct tightness.
4. Inspect weld points for cracks or other defects.
5. Inspect wiring for cuts, nicks or other defects.
6. Inspect hinge post to ensure it is not moving or twisting.
7. Verify charge device for proper operation. Refer to charge controller operation check.
8. Verify monthly that the inside of the control cabinet remains clean and free of insects. Do not spray
control board with bug spray or oil based products.
9. Opening or closing time should be approximately 16 seconds. If the time begins to increase, the
battery needs to be tested.
ENTRAPMENT ZONES
PERIODIC SERVICE