background image

9

3. 

During heating cooling cycle open valves 

C

 and 

D

, close 

valves 

A

 and 

B

.

A.  Maintain a minimum clearance of one (1") inch to 

hot water pipes. In air handling units where they 

may be exposed to refrigerated air circulation, the 

boiler piping system MUST be supplied with flow 

control valves or other automatic means to prevent 

gravity circulation of the boiler water during the 

cooling cycle.

4. 

Hot water boilers installed above radiation level must 

be provided with a low water device either as part of 

the boiler or at the time of boiler installation.

5. 

When a  boiler is connected to a heating system that 

utilizes multiple zoned circulators, each circulator must 

be supplied with a flow control valve to prevent gravity 

circulation.

* Reduced pressure back flow preventer must be 

present under provisions required by the Environmental 

Protection Agency, (EPA).

6. 

Bypass piping is an option which gives the ability to 

adjust the supply boiler water temperature to fit the 

system or condition of the installation. Although, this 

method of piping is not typically required for baseboard 

heating systems.
A.  This method is used to protect systems using 

radiant panels and the material they are encased 

in from high temperature supply water from the 

boiler. 

See Figure 7, page 7.

CONNECTING SUPPLY AND RETURN PIPING

B.  This method is used to protect boilers from 

condensate forming due to low temperature return 

water. Generally noticed in large converted gravity 

systems or other large water volume systems. See 

Figure 8

.

C.  This method is used to protect boilers from 

condensate forming as well as protecting the 

heating system from high water temperature. See 

Figure 9, page 9.

7. 

Note: 

When using bypass piping, adjust valves 

A

 and

 

B

 until desired system temperature is obtained.

8. 

Bypass loop piping must be same size piping for supply 

and return.

9. 

Typical installation using circulators is shown in

 

Figure 10, page 9

.

10. 

Typical installation using zone valves is shown in 

Figure 11, page 10.

11. 

See Figure 12, page 10

 

for typical piping for domestic 

hot water heater.

Figure 8 Bypass Piping Option For Converted Large Volume Systems

Summary of Contents for BC3095

Page 1: ...BOILER INSTALLATION OPERATION MAINTENANCE MANUAL An ISO 9001 2008 Certified Company Manufactured by ECR International Inc 2201 Dwyer Avenue Utica NY 13501 web site www ecrinternational com Models BC3...

Page 2: ...other flammable vapors and liquids DO NOT obstruct air openings to the boiler room Modification substitution or elimination of factory equipped supplied or specified components may result in personal...

Page 3: ...NS Table 1 DIMENSIONS Boiler No Length of Flush Jacket Front of Jacket to Center Line of Flue Outlet Flue Outlet Diameter Tankless Coil to Back of Jacket A B C D BC3 19 9 6 8 BC4 23 11 6 12 Figure 1 D...

Page 4: ...n extensive piping 4 For forced hot water heating systems where boiler and all piping are within the area to be heated select boiler on basis of its Heating Capacity 5 Nozzle listed for use with Becke...

Page 5: ...ion system as practical Allow 24 inches in front top and right hand side for servicing and cleaning or removing tankless water heating coil When installed in utility room door should be wide enough to...

Page 6: ...one starting 12 inches from the top and one 12 inches from the bottom of the enclosed space Each opening shall have a minimum free area of 1 square inch per 1 000 BTU per hour of the total input rati...

Page 7: ...d each opening shall have a minimum free area 1 square inch per 2 000 BTU per hour total input rating of all appliances in the enclosed space See Figure 5 D When ducts are used they shall be of the sa...

Page 8: ...as suggested in Figure 6 When the boiler is used in connection with refrigerated systems A Chilled medium MUST BE IN PARALLEL with boiler B Use appropriate valves to prevent chilled medium from enter...

Page 9: ...o fit the system or condition of the installation Although this method of piping is not typically required for baseboard heating systems A This method is used to protect systems using radiant panels a...

Page 10: ...10 CONNECTING SUPPLY AND RETURN PIPING Figure 9 Bypass Piping Option Used to Protect From Converted Systems With High Water Temperature Figure 10 Typical Installation With Circulators...

Page 11: ...11 CONNECTING SUPPLY AND RETURN PIPING Figure 11 Typical Installation With Valves Figure 12 Typical Installation With DHW...

Page 12: ...ety relief valve outlet and downstream of union if used Terminate pipe with plain end not threaded Refer to local codes and appropriate ASME Boiler and Pressure Vessel Code for additional installation...

Page 13: ...sitive pressure in the combustion chamber Horizontal portions of venting system should not exceed 10 ft in length Horizontal lengths over 10 ft will have negative effect on chimney performance Chimney...

Page 14: ...ended E Compression fittings on suction line often allows air to be drawn into fuel pump making it difficult to maintain oil pressure at the nozzle F Do not run overhead fuel lines from tank to oil bu...

Page 15: ...an inside wall about four feet above the floor 2 NEVER install a thermostat on an outside wall 3 Do not install a thermostat where it will be affected by drafts hot or cold pipes sunlight lighting fi...

Page 16: ...16 WIRING DIAGRAMS Figure 18 Wiring Diagram...

Page 17: ...limit literature for additional information B Burner delay by passed for tankless heat call for heat Burner ignition begins immediately Burner and circulator operation continues until thermostat stops...

Page 18: ...limit point Burner should start B Verify Primary Control and Flame Sensor Flame Failure simulate by shutting off oil supply with hand valve while burner is on Sixty seconds after flameout safety swit...

Page 19: ...ure 17 page 13 5 Disconnect oil line from burner Recommend replacing nozzle at start of each heating season Lubricate burner motor and circulator motor if required with few drops of good grade of ligh...

Page 20: ...ERVICE RECORD Date Nozzle Pump Pressure PSI Smoke Draft CO2 or O2 Flue Temp F Size Angle Type O F INF Controls and Safety Devices X Nozzle Size Angle Type Pump Pressure Vacuum Line Voltage Motor Amps...

Reviews: