Instructions for Use, Installation and Servicing ecoMAX pro
23
Conversion 13
Natural Gas to LPG conversion (ecoMAX pro 28E
only)
The ecoMAX pro 28E is able to be field adjusted for use
on LPG – propane G31 gas. To enable conversion the
use of a combustion analyser is necessary.
Caution!
After converting from Natural Gas to LPG,
re commission and check boiler function as
described in commissioning section of the
servicing and installation instructions.
Caution!
This conversion must only be carried out by a
competent person in accordance with the Gas
Safety (Installation and Use) Regulation 1998.
In the UK CORGI registered installers undertake
the work to a safe and satisfactory standard.
Before starting any work:
Isolate the mains electricity supply to the boiler by
disconnecting the plug at the socket outlet (if there is
only an isolating switch remove the fuse from the switch).
Turn off the gas supply at the gas service valve fitted to
the boiler.
Remove the front panel, the inner front panel and the
lower front panel to access the gas valve.
Turn the gas valve throttle screw (fig 13.4) fully
clockwise.
Turn the throttle back anti-clockwise 5
1
/
2
turns.
Ensure that the gas analyser is set to the correct fuel
setting - Propane.
To obtain conversion follow the procedure as below:
- Connect a CO
2
combustion analyser to the test point on
the flue adaptor.
- Turn on the gas service cock.
- Turn on the electrical supply, and slide the on/off control
down to the ‘I’ position to turn on the boiler. Set the timer
to continuous and turn up any room thermostats to call
for demand.
- With the boiler interface in normal operating mode,
press and hold the ‘mode’ button (
) for 10 seconds
until a flashing ‘0’ appears.
- Press the ‘-‘ key and scroll through until ‘96’ (installer
mode) is shown on the screen, then press the
‘mode’button again.
- Press the ‘+‘ key and scroll through until ‘8’ is shown on
the left of the screen, then press the ‘mode’ button again.
- Set the appliance fan speed/burner to maximum by
pressing the ‘+’ key until ‘2’ (burner to Pmax) is shown
on the right hand side of the screen. Press the ‘mode’
button again to confirm.
- Check the CO2 value, which should be 10.5 % ± 0.2
%. Allow the boiler time to reach the maximum rate
(approximately 5-10 minutes).
- Adjust the maximum rate CO2 with the (‘A’) throttle
using a screwdriver to 10.5 % (rotate anti-clockwise to
increase).
Fig 13.3
12704
Fig 13.2
12703
Fig 13.1
12702
Summary of Contents for ecoMAX pro 18E
Page 37: ...Instructions for Use Installation and Servicing ecoMAX pro 37 Declaration of Conformity 17...
Page 38: ...Instructions for Use Installation and Servicing ecoMAX pro 38...
Page 39: ...Instructions for Use Installation and Servicing ecoMAX pro 39...
Page 40: ...0020005557_04 GB 08 2006 Subject to alteration...