Free-standing tower installation
1. Unpack turbine and check that all components are present. Note that the turbine is
preassembled and checked prior to delivery.
2. Feed the system power cable (recommend 12 AWG) through the mounting pole.
3. Attach the Hyland 920 power cable to the system power cable.
4. Insert the yaw mechanism base on the pole, ensuring that it is fully inserted.
5. Tighten the hose clamp on the base to approximately 4Nm.
6. Secure cabling at the base of the Tower with a 1m loop(s) to allow later removal of the turbine
from the pole if necessary and allow turbine to yaw freely.
7. Run cabling to the controller and connect the three phases of the turbine power to the
controller.
8. Connect the two phases of the output to the battery through a breaker switch. Set the breaker
to ‘off’.
9. On the turbine controller set the SHORT/RUN switch to SHORT. See image below.
10. Remove the cable tie from the Turbine.
11. Turn the battery breaker to ‘on’.
12. On the turbine controller set the SHORT/RUN switch to RUN.
13. Assuming there is wind - the MPPT controller will now power up.
Note: The controller will not be active without turbine power.
Note: See ‘Hyland 920 Controller User Manual’ for controller setup instructions.