Site Preparation
The EURO-ET™ can be connected to guardrail that is assembled tangentially in-line with edge of the
shoulder. Minor site grading may be necessary for the assemblies beyond the edge of the shoulder
to prevent the HBA
®
Bottom Posts (PN 33873A) from extending more than 100 mm above the
ground.
Warning:
Ensure that there is proper site grading for EURO-ET™ placement as
dictated by the specifying agency. Failure to follow this warning could result in serious
injury or death in the event of a collision.
Hinged Breakaway (HBA
®
) Posts
Deploying HBA
®
Bottom Posts
Option (1)
Drive the HBA
®
Bottom Posts (PN 33873A) with an approved driving head to the
appropriate depth(s), approximately 1825 mm. Ensure that the posts are
positioned so that the larger holes in the post plates (ears) are on the
downstream side (see Figures 1 and 2).
Option (2)
To facilitate assembly in extremely hard soil, drill a 300 mm pilot hole
approximately 1825 mm deep and force the HBA Bottom Post (PN 33873A) to the
appropriate depth by impact or vibratory means with an head. approved driving
Note:
If option (2) is used, material should be placed in 150 mm lifts and compacted with
pneumatic equipment to optimum compaction.
Figure 1
Figure 2
Summary of Contents for EURO-ET END TERMINAL
Page 1: ...PN 619489 REVISION D FEBRUARY 2023 EURO ETTM END TERMINAL PRODUCT DESCRIPTION ASSEMBLY MANUAL...
Page 24: ...Valtir com 23 Revision D February 2023 EURO ET Drawing...
Page 25: ...Valtir com 24 Revision D February 2023 Notes...
Page 26: ...Valtir com 25 Revision D February 2023 Notes...