CT-6500 Series 2 Operating Instructions
31
Table 5.0 Close-Open Operation Using Contact Channel #1
STEP
OPERATION
ACTION
DISPLAY
1
READY TIMER FOR BREAKER OPERATION.
PRESS #1 KEY.
INSERTION RESISTOR?
1.NO
2.YES
2
SELECT NO INSERTION RESISTOR.
PRESS #1 KEY.
TIMING WINDOWS:
1.WINDOW = 1 SEC
2.WINDOW = 10 SEC
3.WINDOW = 20 SEC
3
SELECT 1-SECOND WINDOW.
PRESS #1 KEY.
TRIGGER MODE:
1.INTERNAL TRIGGER
2.EXTERNAL TRIGGER
4
SELECT INTERNAL TRIGGER.
PRESS #1 KEY.
TIMING MODE:
1. OPEN
2. CLOSE
3. O-C
4. C-O
5. O-C-O
5
SELECT CLOSE-OPEN OPERATION.
PRESS #4 KEY.
C-O Second Trigger:
1. Contact #1 CLOSE
2. Set DELAY
3. No DELAY
6
SELECT CONTACT #1 CLOSE.
PRESS #1 KEY.
CLOSE-OPEN TIMING
Hold "ARM" Switch
Then "START"
"STOP" to ABORT
7
INITIATE OPEN COMMAND.
HOLD THE "ARM"
SWITCH AND
PRESS THE "START"
KEY.
TEST IN PROGRESS
Hold "ARM" Until
Test complete.
(Up to 25 seconds)
8
ANALYZER IS READY TO OUTPUT RESULTS.
NONE.
1.RUN TEST 06/12/07
2.GET RSLT 19:20:01
3.SET-UP
4.DIAGNOSTIC
NOTE
1. Users can program a delay from 10 to 500 ms between the CLOSE and
OPEN commands. When a delay is used in the operation, it may not
represent a true breaker operating condition.
2. Users can also program in no delay for the operation in which case, the
CLOSE and OPEN commands are initiated at the same time by the CT-6500.
Summary of Contents for CT-6500 2 Series
Page 22: ...CT 6500 Series 2 Operating Instructions 21 Figure 4 0 Series Contact Cable Connection...
Page 77: ...CT 6500 Series 2 Operating Instructions 76 APPENDIX F SIEMENS TCP Breaker Velocity Calculation...
Page 79: ...CT 6500 Series 2 Operating Instructions 78 APPENDIX H CT 6500 SIEMENS SPS2 Test Plan...
Page 82: ...www vanguard instruments com...