9.10.9 Set-Up Open Analysis Points
The following procedure allows the user to set the analysis points to calculate velocity of the circuit
breaker in the open operation. The open analysis point #1 is 1.00 inch from the fully closed
position of the circuit breaker. The open analysis point #2 is 2.00 inches from the fully closed
position.
Table 15.0 Setting Up "OPEN" Analysis Points Using Distance
STEP
OPERATION
ACTION
DISPLAY
1
SELECT SET UP MENU.
PRESS # 3 KEY.
1.ANALYSIS POINT
2.MEASUREMENT UNITS
3.SAVE / RESTORE
4.NEXT PAGE
2
SELECT ANALYSIS POINT.
PRESS # 1 KEY.
1.OPEN TIMING
2.CLOSE TIMING
3.PRINT SETTING
4.TEST PLAN
3
SELECT OPEN TIMING.
PRESS # 1 KEY.
OPEN ANALYSIS PT 1
1.PERCENT OF STROKE
2.DISTANCE FROM CLOSE
3.CONTACT #1
4
SELECT DISTANCE FROM CLOSE.
PRESS # 2 KEY.
OPEN ANALYSIS PT 1
DISTANCE FROM CLOSE
VALUE: XX.XX in
"ENTER" TO CONFIRM
5
ENTER 1 INCH.
PRESS KEYS 0-9 TO
SET 1.00. USE THE
“ENTER” KEY TO
CONFIRM.
OPEN ANALYSIS PT 1
DISTANCE FROM CLOSE
VALUE: 01.00 in
"ENTER" TO CONFIRM
6
CONFIRM ENTRY.
PRESS THE "ENTER"
KEY.
OPEN ANALYSIS PT 2
1.PERCENTAGE OF STROKE
2.DISTANCE FROM CLOSE
3.C/- TIME
7
SELECT DISTANCE FROM CLOSE.
PRESS # 2 KEY.
OPEN ANALYSIS PT 2
DISTANCE FROM CLOSE
VALUE: XX.XX in
"ENTER" TO CONFIRM
8
ENTER 2 INCHES.
PRESS KEYS 0-9 TO
SET 2.00 INCHES.
OPEN ANALYSIS PT 2
DISTANCE FROM CLOSE
VALUE: 02.00 in
"ENTER" TO CONFIRM
9
RETURN TO MAIN MENU.
PRESS THE "ENTER"
KEY.
1.RUN TEST 06/10/07
2.GET RESULTS 20:10:01
3.SETUP
4.DIAGNOSTIC
Summary of Contents for CT-6500 2 Series
Page 22: ...CT 6500 Series 2 Operating Instructions 21 Figure 4 0 Series Contact Cable Connection...
Page 77: ...CT 6500 Series 2 Operating Instructions 76 APPENDIX F SIEMENS TCP Breaker Velocity Calculation...
Page 79: ...CT 6500 Series 2 Operating Instructions 78 APPENDIX H CT 6500 SIEMENS SPS2 Test Plan...
Page 82: ...www vanguard instruments com...