I N S T A L L A T I O N
V A N T A G E C O N T R O L S . C O M
1061 South 800 East • Orem, Utah 84097 • Telephone 801 229 2800 • Fax 801 224 0355
TPT1210-1 IN WALL DOCK — MODEL: TPT1210-1-IW
Overview
Vantage’s in-wall TPT1210-1 In-Wall Docking station allows the
TPT1210-1 to be easily docked in the wall. The dock provides
full Ethernet hardwire connectivity including power, charging
the battery while docked. All functionality of the TPT1210-1
remains continually active while docked, making this a
comfortable, secure interface. The in-wall Dock securely holds
the TPT1210-1, freeing both hands for touchscreen navigation
and operation. The in-wall dock is designed to maintain a clean
finished look even when the touchscreen is not mounted.
The
TPT1210-1-IW
may be installed as a retrofit using the two
telescoping rails included. A pre-installed option is also
available, using the rough-in KIT, part number
TPT1210-
1-INSTALL-16
. Please see the two methods below.
System Specifications/Requirements
Description
Specification
Overall Dimensions,
HWD
11” x 13.75” x 3.25”
279mm x 349mm x 83mm
Surface Dimensions,
HWD
11” x 13.75” x 0.25”
279mm x 349mm x 6mm
Back Box Dimensions,
HWD
9.5” x 12.5” x 3”
241mm x 318mm x 76mm
Weight
8.0 lbs. – 3.6 kg
Retrofit Mounting
Mounts to two 16inch telescoping brackets
(included)
Pre-Installation
Mounting
Mounts to TPT1210-1-INSTALL-16
PLEASE SEE:
TPT1210-1-INSTALL-16_install.pdf
Installation sheet
Power Connection
Inside Electrical Box – 120/240V
Built-In AC Adapter
100~240V, AC 47~63Hz, 19V DC output,
3.16A 60W Adapter
Operating Temperature
5°C ~ 35°C (41° F ~ 95° F)
Ambient Operating
Humidity
5-95% non-condensing
System Requirements
This dock is compatible with all Vantage TPT1210-1 tablets.
Installation
Installation of Vantage products should be performed or
supervised by a
Certified Vantage Installer. Please read all of
these instructions before beginning. Turn the circuit breaker off
and make sure no voltage is present where the
dock is to be mounted
. Damage caused by failure to
disconnect power may void the warranty and is a risk to
the installer.
Mac Address
If using the hard-wired Ethernet connection in your installation,
be sure to record the MAC address of the TPT1210-1 IN WALL
DOCK. This information may be needed in setting up the local
network.
This product must be mounted vertically
for proper performance.
See page two for proper procedure to
open the TPT1210-1-IW dock for
installation.
Location/Electrical:
•
The recommended mounting wall
height is six inches above that of a
typical keypad station or approximately
50” to 58” from the floor to the bottom
of the dock. However, it may be
installed at any height fitting
your
installation requirements.
•
Connect the high voltage wires from the dock to standard
house wiring, using approved high voltage wire connectors.
•
Wiring:
o
LINE = Black -or- Brown, depends on power supply
o
NEUTRAL = White -or- Blue, depends on power supply
o
GROUND = Green with Yellow Stripe
1. Mounting Option One, TPT1210-1-IW Mounted to
TPT1210-1-INSTALL-16 Box:
•
The
TPT1210-1-INSTALL-16
KIT should already be installed.
•
Network RJ-45 and house wiring service leads should
already be inside the
TPT1210-1-INSTALL-16
KIT (through
the bottom).
•
The bottom of the
TPT1210-1-IW
contains a standard
Female RJ-45 connector.
•
Plug in the internet connection
•
Connect AC power to 1210 Dock conforming to standard
National Electrical code. See wire colors above.
•
Carefully slide the
TPT1210-1-IW
over the four mounting
screw posts inside the
TPT1210-1-INSTALL-16
box. Secure
with the four wing-nuts provided in the
TPT1210-1-INSTALL-
16 KIT
•
Make sure the
TPT1210-1-IW
is level before tightening the
four wing nuts
2. Mounting Option Two, Retrofit:
•
Cut sheetrock hole exactly
12.75" wide x 9.75" high
:
•
Install two telescoping brackets to the framing inside the
hole (brackets included).
o
Bend the brackets inward 90 degrees at each end
o
The mounting side of the telescoping bracket must be
3 and 1/8” (inches) back from the
front
of the sheet
rock. (See page 3 below)
o
The two telescoping brackets must be positioned to
line up with the four screw slots (see picture 5 below)
•
Connect AC power to the TPT1210-1 Dock conforming to
standard National Electrical code. Electrical connections
must be made inside the connection area in the bottom of
the
TPT1210-1-IW
.
•
Secure the TPT1210-1-IW using 4 screws connected to the
telescoping brackets.
•
DO NOT OVER-TIGHTEN
Mounting/Dismounting TPT1210-1 On the Floating Dock
Plate
MOUNT:
•
Dock the 1210-1 tablet by inserting the bottom first into the
self guiding cupped tray.
•
Carefully press back the top of the TPT1210-1 tablet to
completely lock the docking clamps.
•
Make sure it is locked before leaving by sliding the lock
lever on the top.
•
Press the tablet all the way back (until it bottoms) and then
release to secure in the wall
REMOVE:
•
Press the tablet all the way back (until it bottoms) and then
release to allow the Floating Dock to release from the wall
•
Unlock by sliding the lock lever on the top
•
Remove the TPT1210-1 by pressing
in
either the left or right
side levers and carefully tilting the top of the TPT1210-1
away from the wall while leaving the bottom securely in the
cupped tray.
•
Finish by carefully lifting the TPT1210-1 from the tray.
IMPORTANT
:
Latch Kit must be
installed to lock
the screen to the
dock. Screw the
Latch Bracket to
the back of the
TPT1210-1
Touchscreen using