2.6 Nitrogen Purge Option
A continuous purge of the 959D roughing pump and the associated vacuum system in the
leak detector with laboratory grade nitrogen will assure that residual helium levels do not
raise the system background to unacceptable levels. The N
2
purge option consists of an
inlet port with a pressure-relief valve and a flowmeter mounted on the bottom of the cart
adjacent to the roughing pump as is seen in Figure 2-9. The nitrogen is introduced to the
system via a port on the roughing pump, from where it flows through the pump toward the
leak detector and replaces and then blocks the entry of ambient helium.
To set up the nitrogen purge:
1. Remove the plug on the nitrogen port and connect the N
2
as shown in Figure 2-9.
2. Adjust the flow meter to by rotating the knob at its base to 5 liters/minute.
For more information about the role of the nitrogen purge feature, contact Varian Vacuum
Technologies Customer Service at 1-800-8VARIAN. If the leak detector is not going to be
used for a few hours, the N
2
flow should be closed off.
Figure 2-9
N
2
Purge System
Pressure
Labels
Summary of Contents for 959D
Page 16: ...959D Leak Detector 1 2 D R A F T 9 1 3 0 2 Figure 1 1 Model 959D Leak Detector ...
Page 28: ...959D Leak Detector This page intentionally left blank D R A F T 9 1 3 0 2 ...
Page 48: ...959D Leak Detector This page intentionally left blank D R A F T 9 1 3 0 2 ...
Page 68: ...959D Leak Detector This page intentionally left blank D R A F T 9 1 3 0 2 ...
Page 78: ...959D Leak Detector This page intentionally left blank D R A F T 9 1 3 0 2 ...
Page 81: ......