Connections to the distributor box
8.6.1
The following connections must be prepared:
Device connection:
Recommendation: 3 x 2.5 mm²
Sensor cable: RJ12 (included in delivery)
LAN connection
i
1. Do not allow any mechanical load on the
sensor cable.
2. In order to minimise losses, the wiring
section between storage and connection
should not be longer than 20 m.
Preparation of the AC port for the building grid
8.6.2
Figure 10: Stripping cables
To connect to the building grid, the 3-wire AC cable must be
connected to the supplied AC connector.
Strip the cable 55 mm at the end.
The PE conductor must be 8 mm longer than the other four
conductors. Shorten these conductors accordingly.
Strip the insulation off the ends of the conductors in the
cable for a length of approx. 9 mm.