31
Connections at distribution
The following connections are to be prepared:
Device connection:
Recommendation: 3 x 2.5 mm
²
,
Sensor cable: RJ12 (in scope of delivery),
LAN connection.
Do not expose the sensor cable to a mechanical load.
To keep the losses low, the line distance between the store and the connection should be
no more than
20 metres.
Preparation of AC connection house network
For the connection to the house network, the 3-wire AC connection line must be connected to the AC
plug connection included in the delivery.
Strip the connection line 55 mm at the end.
The PE conductor must be 8 mm longer than the other conductors. Shorten these conductors
accordingly.
Strip the wires of the line at the ends approximately 9 mm.
Connecting a single-wired conductor: Feed in the stripped conductor until it can go no further.
Connecting a fine-wired conductor: Actuate clamping spring
using screwdriver (2.5 mm blade width). Feed in the stripped
conductor until it can go no further.
To loosen the line, actuate the spring using the screwdriver.
Bring the connection cable into shape.
Latch the cord grip housing onto the adapter and insert the cable.
Lock the upper part of the cord grip into place and tighten with the screw.
1 AC plug
2 Cord grip housing (lower part)
3 Cord grip housing (top part)
Summary of Contents for pulse neo
Page 1: ...VARTA STORAGE GMBH OPERATING MANUAL VARTA pulse neo ...
Page 35: ...35 All dimensions in millimetres Fig 2 Dimensions on the support plate ...
Page 77: ...As at 07 2021 Appendix a Connection diagram TN C network ...
Page 78: ...As at 07 2021 Appendix b Connection diagram TT network ...
Page 79: ...As at 07 2021 Appendix c Connection diagram TN C network with data logger ...
Page 80: ...As at 07 2021 Appendix d Connection diagram TT network with data logger ...