47
Please restart the function test.
If the test fails again:
Ensure that the cabling was performed correctly.
Switch off the energy storage system. The already entered data remain intact.
Carry out the steps again.
Should the remedial actions described remain unsuccessful, please contact the VARTA
Service.
Completing the configuration
After carrying out the configuration, complete the installation by clicking on the
“Complete”
button.
Note:
If the installation report is to be saved on the computer, then actuate the
“Save report”
button.
Individual mode option
: Once the function test has been completed successfully, you can complete
the installation of the installation assistant. You come to the homepage of the web interface. Here
you can perform further configurations and access current values.
Cascade mode option:
As soon as the installation assistant has been completed and the function test
was successful, you come directly into the Cascade Manager.
Cascade mode
As soon as the function test is passed, the “Cascade Manager” is called up.
Select the current sensor configuration.
Enter the necessary information for the store to be coupled.
Note:
If you use the VARTA link as the current sensor, enter the
IP address
of the
VARTA
link
.
Actuate the
“Connect”
button.
The connected store is displayed in the overview “Coupled stores”.
Once a store is coupled and the VARTA pulse neo can access the data from the store, the “cascade
monitor” is displayed.
Here you receive an overview of the complete cascade:
charge status of the cascade,
the currently implemented performance,
the max. capacity of the cascade,
If you want to connect several stores, then carry out the installation in the “Cascade Manager” again.
Note:
Up to 5 devices can be coupled.
Note:
Please do not forget to register the guarantee of the energy storage system in the
VARTA portal. To this end, ensure that the device is connected to the customer’s network
and that there is an internet connection.
Summary of Contents for pulse neo
Page 1: ...VARTA STORAGE GMBH OPERATING MANUAL VARTA pulse neo ...
Page 35: ...35 All dimensions in millimetres Fig 2 Dimensions on the support plate ...
Page 77: ...As at 07 2021 Appendix a Connection diagram TN C network ...
Page 78: ...As at 07 2021 Appendix b Connection diagram TT network ...
Page 79: ...As at 07 2021 Appendix c Connection diagram TN C network with data logger ...
Page 80: ...As at 07 2021 Appendix d Connection diagram TT network with data logger ...