51
Check whether the wall fastening is stable.
o
If necessary, tighten the screw or replace it.
Checking the system parameters
The system parameters are checked via the web interface. For this, see chapter 13.
Air filter change: Reset time
The air filter must be replaced at every second service. See chapter 14.4.9.
Select
â
Settings
â
Service.
Actuate the button.
Checking the current sensor values
Check the current sensor values (I network L1, I network L2 and I network L3) to ensure that they
are
realistic
values.
Measures in the event of value 0:
If a current sensor value is approximately 0, even though this phase is currently charged, it may be
that the connection between the current sensor and the energy storage system is faulty.
In this case, if necessary, charge all the phases separately: Switch on consumers systematically.
If necessary, check the current flow through all three phases with the clamp-on ammeter.
Measures in the event of conspicuous current sensor values:
Check whether the connection was performed as a clockwise rotating field.
If, despite the charge, the current sensor value of one or several phases is 0, check the connection
between the energy storage system and the current sensor.
If necessary, replace the connection line (RJ12 cable).
Check battery converter
Check the status of the battery converter for plausibility
Check the battery module
Check whether warnings and errors of the battery module are displayed.
Service and repair: Housing interior
Opening the energy store
Ensure that the energy store is switched off.
To open the energy store, unscrew the screws on the lower side of
the hood.
Aid:
Torx 20 screwdriver
Pull the hood approximately 30 cm away from the wall at the
lower side.
Separate the earthing connection between the hood and the battery converter.
To this end, loosen the block.
Remove the hood upwards.
Converter AC side
Summary of Contents for pulse neo
Page 1: ...VARTA STORAGE GMBH OPERATING MANUAL VARTA pulse neo ...
Page 35: ...35 All dimensions in millimetres Fig 2 Dimensions on the support plate ...
Page 77: ...As at 07 2021 Appendix a Connection diagram TN C network ...
Page 78: ...As at 07 2021 Appendix b Connection diagram TT network ...
Page 79: ...As at 07 2021 Appendix c Connection diagram TN C network with data logger ...
Page 80: ...As at 07 2021 Appendix d Connection diagram TT network with data logger ...