2 Site Prep - International Installations
General
This document describes the procedures necessary to prepare the site, ready for the installation of the Veeder–
Root TLS Series Underground Storage Tank Monitoring Systems.
This manual does
not
cover the site preparation necessary for the installation of Veeder–Root Delivery Information
Systems (DIS). For information on these products please refer to the relevant manuals.
Veeder–Root maintains a continuous process of product development and therefore product specifications may
not be as described in this manual. Please contact the Veeder-Root office nearest you, or visit our website at
www.veeder.com
for information on new or updated products. Changes affecting products or procedures
described in this manual will be reported in subsequent revisions. Veeder–Root has taken every care in the
compilation of this manual; however it is the installers' responsibility to take every precaution to safeguard
themselves and others.
Every person working with Veeder–Root equipment is expected to take every safety precaution possible and to
have read this manual, particularly the sections referring to health and safety.
Deviation from the specifications contained in this manual can result in rework, delays in
system installation and additional installation charges.
Contractors are advised to contact their nearest Veeder–Root office where local conditions may preclude using
the specifications contained in this manual.
INSTALLATION LEVELS
Veeder–Root require that certain facilities are installed by contractors, nominated by the customer, prior to
Veeder–Root attending the site for the installation of a TLS-IB system. These facilities vary dependent on the
installation contract agreed between Veeder–Root and the customer. Two levels of site preparation exist and are
described below:
Level 1 Installation
The customer or his elected contractor will supply (unless stated otherwise) and install the following:
• Console power supply and earth.
• External devices power supply and cabling.
• Peripheral devices cabling.
• Probe cable ducting
• Probe field cables
• Probe risers
• The contractor will seal all ducting after system testing has been carried out.
Level 2 Installation
The contractor will install the following:
• TLS-IB power supply and earth.
• External devices power supply and cabling.
NOTICE