Operations sequence
General instructions
37
cpg
.1
Fully SF6 gas insulated single and double busbar GIS switchgears up to 36 kV in accordance
with IEC Standards
IG-137-EN version 03; 24/06/2016
7.1.1 Commissioning from open position
Initial conditions
: Circuit breaker open, feeder
disconnector open and earthing switch open.
1. Connect the feeder disconnector by turning the lever
clockwise.
Figure 7.2
Lever turn detail
2. Then close the circuit breaker by acting on the “I” top
pushbutton.
Figure 7.3
“I” pushbutton detail
To remove from service, proceed in reverse
order using the “0” pushbutton.
Summary of Contents for Ormazabal cpg.1 Series
Page 67: ......