Operations sequence
General instructions
39
cpg
.1
Fully SF6 gas insulated single and double busbar GIS switchgears up to 36 kV in accordance
with IEC Standards
IG-137-EN version 03; 24/06/2016
7.2
cpg.1-v2
cubicle
Figure 7.6
Initial situation of the
cpg.1-v2
cubicle
7.2.1 Commissioning from open position
Initial conditions
: circuit breaker open, main
feeder disconnector closed, secondary feeder
disconnector open and earthing switch open.
1. Connect the required feeder disconnector by turning
the lever clockwise.
Figure 7.7
Lever turn detail
2. Then close the circuit breaker by acting on the “I” top
pushbutton.
Figure 7.8
“I” top pushbutton detail
To remove from service, proceed in reverse
order using the “0” opening pushbutton.