IG-322-EN version 03; 22/07/2022
40
Operation
General instructions
SF
6
-insulated circuit-breaker panel:
Type
gae
.630 -1LSV(G)-/5/
in modular extensible design up to 24 kV, 20 kA
5.4. Switching the circuit-breaker panel
5.4.1. Inspection activities and safety instructions
Danger to life due to arc fault!
Before each switching operation, the gas filling
pressure must be checked (see chapter 4.4 and
chapter 4.5)!
The function of the capacitive voltage detecting
system must be checked before each switching
operation (see chapter 6.5). All phases (L1, L2, L3) must
always be checked!
Prior to the switching, the front cover must be inserted.
• Check the switching readiness (see warning message).
Before switching the circuit-breaker switch the fastener
must be closed with the fastener key (Figure 5.8).
The disconnector and earthing switch are mechanically
locked with each other.
If the earthing switch is switched ON the plug-in
opening on the switching shaft of the corresponding
disconnector switch is closed by a locking plate.
The switching state of the disconnector and earthing switch
can be read off the switch position indicators in the circuit-
breaker panels mimic diagram (Figure 5.9).
32572056
1
2
1
Open
2
Closed
Figure 5.8.
OFF
ON
Figure 5.9.