Initial Setup
SECTION 3
6
Installing Center Hub:
The VMI Hybrid unit
comes with six Center Hubs. These hubs protect
the inside diameter of the disc, from collecting
any residue, during the repair process. The
Center Hub will need to be replaced after 84
minutes of use. This will occur at the same time
that the Buffing Pads need to be replaced. The
Center Hub should be installed after the Buffing
Solution and the Water lines have been prepped.
Locate the metal Hex shaped post between the
two Buffing Pad Holders. Take one of the Center
Hubs and line up the Hex shaped opening on the hub with the Hex shaped post.
Push the Center Hub in, as far as it can go. Spin the Center Hub by hand to make sure
the hub is centered. If needed, make the proper adjustment.
Installing Buffing Pads:
The VMI Hybrid unit
comes with six sets of Buffing Pads, which are
good for a total of 500 minutes, 84 minutes per
set. These Buffing Pads are not pre installed!
Note: Installation of the Buffing Pads is
recommended to be done after the prepping
of the Buffing Solution and Water lines. This
will prevent any undue Buffing Solution or
Water from contaminating the buffing pads.
Install each buffing pad onto the buffing pad
holder. Each Buffing Pad has been marked on
the back side with an “L” or an “R”, to indicate
which Buffing Pad should go on which Buffing
Pad holder.
NOTE: THE “R” (RIGHT) BUFFING PAD
IS LARGER IN SIZE THAN THE “L” (LEFT) BUFFING
PAD.
Make sure that the Buffing Pad is centered
and fully seated on the Buffing Pad Holder.
After every 84 minutes of machine use, the VMI
Hybrid will inform the Operator to replace the Buffing Pads.
CAUTION: IT IS ESSENTIAL TO KEEP THE “TOP COVER” IN THE OPEN POSITION WHEN
THE MACHINE IS IN THE “ STAND BY” MODE & WHEN THE MACHINE IS NOT IN USE!
THIS WILL ENSURE THAT THE BUFFING PADS WILL NOT BECOME FLAT.
Your VMI Hybrid unit is now ready to be used!