Technical Specification & Installation
Sentinel Kinetic MVHR Installation & Commissioning
6
Overview
The following instructions are intended to help prevent potential hazards and installation should only be carried out
by a qualified electrician and installer.
Before Installation of the Unit
Inspect the Unit
When taking delivery of the unit, check the items delivered against the enclosed delivery note. Inspect the unit for
damage in transit. If in doubt, contact Customer Services. Each box contains a Kinetic unit, anti-vibration mounts
and product documentation. In addition the Sentinel Kinetic 200ZP and ZPH models include a remote control and
cable.
Lift and Move the Unit Safely
Check the weight of the unit that you are installing. Always use appropriate lifting techniques and appliances when
moving heavy equipment.
Check Site Requirements and Safety Notices
Check that the physical and environmental conditions for the site meet, or exceed, the requirements detailed in the
Technical Specification
.
Unit Installation
The unit MUST always be mounted horizontally. Do not use this unit as a support for any other equipment.
The ceiling should have sufficient strength to support the unit.
Take into consideration the position of the electrical services and the condensate drain.
Ensure there is adequate access for installation, operation and maintenance.
It is recommended that a local disconnection mains and sensor terminal box is installed within 1m of the unit to
facilitate future maintenance.