IMPORTANT SAFETY INFORMATION 
 

PLEASE READ THESE 
INSTRUCTIONS CAREFULLY 
BEFORE COMMENCING 
INSTALLATION. 

1. Do not install this product in areas where the 
following may be present or occur: 

•  Excessive oil or a grease laden atmosphere. 

•  Corrosive or flammable gases, liquids or vapours. 

•  Subject to direct water spray from hoses. 

•  Ambient temperatures higher than 40°C and lower 
than -20°C. 

•  Possible obstructions that may hinder access to or 
removal of the unit. 

2. All wiring must be in accordance with the current 
IEE wiring regulations BS7671, or appropriate 
standards of your country. Installation should be 
inspected and tested by a suitably qualified person 
after completion. 

3. Ensure the mains supply (voltage, frequency and 
phase) complies with the rating label. 

4. The unit should be provided with a local double 
pole fused spur fitted with a 3A fuse having a contact 
separation of at least 3mm. 

5. These units must be earthed. 

6. Precautions must be taken to avoid the back-flow 
of gases into the building from the open flue of gas or 
other fuel-burning appliances. 

7. This appliance is not intended for use by persons 
(including children) with reduced physical, sensory or 
mental capabilities, or lack of experience and 
knowledge, unless they have been given supervision 
or instruction concerning use of the appliance by a 
person responsible for their safety. 

8. Young children should be supervised to ensure 
that they do not play with the appliance. 

INSTALLATION GUIDANCE 

1. The installer is responsible for the installation and 
electrical connection of the sentinel system on site. It 
is the responsibility of the installer to ensure that the 
equipment is safely and securely installed and left 
only when mechanically and electrically safe. 

2. All regulations and requirements must be strictly 
followed to prevent hazards to life and property, both 
during and after installation, and during any 
subsequent servicing and maintenance. 

3. The unit’s condensate drain must be connected to 
the building’s wastewater drainage system. 

4. Certain applications may require the installation of 
sound attenuation to achieve the sound levels 
required. 

5. The unit must not be connected directly to a 
tumble drier. 

6. The supply and exhaust valves must be fully 
opened prior to commissioning. 

7. The supply air must be drawn from the exterior of 
the property. 

8. The unit should be allowed to stabilise during 
commissioning for a minimum period of 5 minutes 
when changing between boost and normal speeds. 

9. Ensure that the unit’s external grilles are a 
minimum of 1500mm apart. The exhaust grille should 
be located at least 600mm away from any flue outlet. 
The inlet grille should  be located 2000mm away from 
any flue outlet. 

10. This product and associated duct installation 
should be carried out in accordance with the 
domestic ventilation compliance guide. 

 

Disposal 

This product should not be disposed of 
with household waste. Please recycle 
where facilities exist. Check with your 
local authority for recycling advice.

Summary of Contents for HR200V

Page 1: ...HR200V Ducted Heat Recovery Ventilator Installation and Maintenance Instructions PLEASE READ INSTRUCTIONS IN CONJUNCTION WITH ILLUSTRATIONS PLEASE SAVE THESE INSTRUCTIONS Stock Ref No HR200V 14120010...

Page 2: ...re that they do not play with the appliance INSTALLATION GUIDANCE 1 The installer is responsible for the installation and electrical connection of the sentinel system on site It is the responsibility...

Page 3: ...3 Warnings Safety Information Contents Section Page 1 0 Introduction 4 2 0 Site Requirements 5 3 0 Installation 6 4 0 Electrical 8 5 0 Maintenance 9...

Page 4: ...lation ducting 3 The maximum power consumption for the unit is 108w 4 The twin impeller and heat exchanger arrangement simultaneously supplies and extracts air while transferring heat from the stale e...

Page 5: ...he unit must be sited such that the ambient temperature will not exceed 40 C 9 Do not site the appliance in the vicinity of excessive levels of airborne oil or grease 10 If the unit is installed in a...

Page 6: ...ect an approved electrical control arrangement for the HR200 unit above 2 After considering the site requirements Section 2 0 select a suitable site for the unit and controllers and work out the cable...

Page 7: ...he installation site and fix it in position using four suitable screws and the remaining four supplied washers The washers should be located between the screw heads and the mounting grommets CAUTION E...

Page 8: ...es as shown in Fig 5 to a Switched fused spur or a control unit If a controller is used follow the fitting and wiring instructions supplied with the controller ensuring that the black and brown wires...

Page 9: ...of contamination experienced and according to the following procedure 3 Isolate the mains power supply 4 Remove the ducting to internal grilles Undo the two grille securing screws and remove the spig...

Page 10: ...Control Declared Max Internal External Leakage Rates for BVUs or carry over for regenerative heat exchangers only Ext Leakage Rates for Ducted UVUs 5 Internal 5 External Mixing Rate of Non Ducted BVU...

Page 11: ......

Page 12: ...rating label attached to the unit Has not been subjected to misuse neglect or damage Has not been modified or repaired by any person not authorised by the company IF CLAIMING UNDER TERMS OF GUARANTEE...

Reviews: