Installation
Sentinel Kinetic MVHR Installation & Commissioning
19
Wall Mounting Sentinel Kinetic Plus
1.
Refit the front and rear covers if they have been
removed.
2.
Ensure five off wall bushes are fitted to the rear cover,
three along the top row of screws and two along the
middle row.
3.
Mark the condensate and wall bracket positions using
the template on page 20. A paper copy can be
obtained from Vent-Axia Technical Support.
4.
Fit 2-off metal wall brackets (supplied) to the wall using
appropriate fixings.
5.
Lift unit and locate the wall bushes onto the 2 wall
brackets. The unit should now be physically installed in
its intended operating location.
6.
Ensure that the condensate drain is connected.