STAGEMAKER®
-
32
VERLINDE reserves the right to alter or amend the above information without notice.
11/2008
9.1 Electricity
,
Before any operation on the electric box, check that the hoist supply is disconnected.
,
The single phase hoists are provided with capacitors. Before any operation in the electric
box, please check that the capacitor is unloaded by means of a voltmeter in Vdc setting.
,
An isolator switch should be installed at a maximum of 6 meters from the hoist.
9.1.1 Electrical
connection
The customer must supply the power supply cable, the fuses and the main isolator switch
(refer to the wiring diagram).
Check that the mains system is correct for the hoist.
Check that the voltage does not vary by more than + 5% from the nominal value.
Neutralize the electric sources.
Make sure that the main hoist electric power switch is off.
Do not use binding posts (luster terminals, etc.) to connect the
power supply cable to the hoist.
Do not use rigid cable or cable with a section different to that
indicated below to supply the hoist.
Never shunt the isolators, the power switches or the limitation or
prevention equipment.
Never block, adjust or remove the limit stops or switches to go
higher or lower than these allow.
9.1.2 Connection
:
•
Remove the control box cover.
•
Insert the cable (PS) into the box through the PG cable
gland.
•
In case of a power supply with 2 phases, connect L1 and
L2 to the terminal 1 and 2. In case of power supply with 1
phase and neutral, connect N (neutral) to the terminal 1
and L2 to the terminal 2.
•
Check that the terminals are correctly tightened.
•
Close the box.
•
Check the hoist operation
Minimum cable sections :
Power supply :
1,50 mm²
Control box/hoist :
1,00 mm²
Fuses (low voltage) :
See electric
power supply (
customer supply
) :
Drawing
Do not use the controls needlessly
(avoid inching-stop-start operation)