VenTInG InSTallaTIon
Example:
Elbow 1 = 90°
Elbow 2 = 45°
Elbow 3 = 45°
Elbow 4 = 90°
Total Angular Variation = 270°
24" (610 mm)
Min.
1
2
3
4
1
2
3
4
FP1179
max bends
Figure 22 -
Maximum Elbow
Usage
FP1179
InSTallaTIon For VerTIcal TerMIna-
TIon
1. Determine the route your vertical venting will take. If
ceiling joist, roof rafters or other framing will obstruct
the venting system, consider an offset.
Refer to Figure
24
to avoid cutting load bearing members.
FP1969
offset w/ wallstrap
Figure 23 -
Offset with Wall Strap and 45° Elbows
Roof Flashing
Wall Strap
45° Elbows
Ceiling Firestop
FP1669
For optimal flame appearance, a restrictor disk is necessary
on straight vertical runs of 10' of more.
•
Runs may not incorporate elbows.
•
The disk is part number 56D3027 and is included in
installation manual packet.
•
Drop the disk into a 5" inner collar before installing the
first section of flue or install at the last section before
installing the termination. Also disk can be installed
from inside the firebox into the 5" inner collar.
•
An additional disk may be installed on runs of 35' or
more. Rotate disks perpendicular to each other.
noTe:
Pay special attention to these installation instructions
for required clearances (air space) to combustibles when
passing through ceilings, walls, roofs, enclosures, attic
rafters, etc. Do not pack air spaces with insulation. Also
note maximum vertical rise of the venting system and any
maximum horizontal offset limitations. Offsets must fall
within the parameters shown in
Figures 24 and 25
.
2. Set fireplace in desired location. Drop a line plumb down
from the ceiling to the position of the flue exit. Mark the
center point where the vent will penetrate the ceiling.
Drill a small locating hole a this point.
Drop a plumb line from the inside of the roof to the ceiling
locating hole in the ceiling. Mark the center point where
the vent will penetrate the roof. Drill a small locating hole
at this point.
FlaT ceIlInG InSTallaTIon
1. Cut a 10
Z\x
" (241 mm) square hole in the ceiling using the
locating hole as a center point The opening should be
framed to 10
Z\x
"x10
Z\x
" (267 x 267 mm) inside dimensions
as shown in
Figure 25
using framing lumber the same
size as the ceiling joist. If the area above the ceiling is
an insulated ceiling or a room, nail firestop from the top
side. This prevents loose insulation from falling into the
required clearance space.
Figure 23.
Otherwise, install
firestop below the framed hole.
Figure 25
FP1969
firestop w room above
Figure 24 -
If Area Above is a Room, Install Firestop above
Framed Hole as Shown
Firestop