Operating URCap and Running CNC Programs
•
This URCap comes with two nodes:
•
VB: Run Haas Legacy
•
VB: Wait for Haas Legacy
•
The two nodes are used together but do not need to be
placed consecutively
•
After selecting the
VB: Run Haas Legacy
node a new line will
appear in the Robot Program
called
Run CNC Program: 0
–
Where the zero will be replaced with milling program
number
•
Enter a valid
CNC Milling Program
. Zero is not an
allowed program number, and the node will not be
marked complete until a valid program number is
entered
•
Communication Settings can be ignored as long as
default values are acceptable. See Appendix B on
how and why to use other values
August 2019
VersaBuilt Robotics
25
Summary of Contents for 5003870
Page 5: ...Connect Ethernet Cable and Cycle Start Relay August 2019 VersaBuilt Robotics 5 ...
Page 8: ...Cycle Start Relay Connecting to Haas CNC Controller August 2019 VersaBuilt Robotics 8 ...
Page 13: ...Electrical Diagram Connecting to UR Control Box August 2019 VersaBuilt Robotics 13 ...
Page 14: ...Install Software on UR Teach Pendant and Haas Controller ...
Page 24: ...Operate Using the Teach Pendant Commands to run CNC programs ...