Vertiv™ XTE 802G Generator Room Walk-In-Cabinet Description and Installation Manual
22
5
Installation Considerations
NOTE!
If holes are drilled into the exterior of this XTE 802G and not filled using a seal tight connector, the manufacturer’s
warranty will be void.
5.1
Important Safety Instructions
DANGER!
Adhere to the “Important Safety Instructions” starting on page vi.
5.2
Installation Overview
The following is the recommended sequence for the installation and start-up procedures. The sequence may change according to job
and site conditions.
•
Ensure all site drawings and approvals are in place.
•
Obtain the recommended tools and test equipment.
•
Read “Important Safety Instructions” starting on page vi carefully.
•
Check that all the equipment and materials have been delivered.
•
Proceed with the physical installation of the XTE 802G.
•
Install and verify ground cables.
•
Install and verify the DC power.
•
Route, splice, and verify the OSP cables.
•
Install and verify the alarm cables.