Installation
15 of 36
IM-HC 561174 1120 Basic Heating Control
5. The control lifts up and away from the base, which is ready for
mounting.
6. Wiring can enter from bottom or back of enclosure. Knockouts allow
wiring to be run in conduit.
4.1.2 Rough-In
All electrical wiring terminates in the control base wiring chamber. The
base has standard 7/8" (22 mm) knockouts, which accept common wiring
hardware and conduit fittings. Before removing the knockouts, check the
wiring diagram and select those sections of the chamber with common
voltages. Do not allow the wiring to cross between sections as the wires
will interfere with safety dividers that should be installed at a later time.
Power must not be applied to any of the wires during the rough-in wiring
stage.
■
Install the Outdoor Sensor and Supply Sensor according to the
instructions on the next two pages and run the wiring back to the control.
■
If an Indoor Sensor (optional) is used, install the sensor according to
the instructions included with it and run the wiring back to the control.
■
Run wire from other system components (circulator pump, boiler,
actuating motor, etc.) to the control.
■
Run wires from the 120V AC power to the control. Use a clean power
source to ensure proper operation. Multi-strand 16 AWG wire is
recommended for all 120V AC wiring due to its superior flexibility and
ease of installation into the terminals.