36
Supply (flow) pres-
sure for natural
gas
Supply (flow)
pressure for LPG
Measures
below 15 mbar
below 25 mbar
Do not start the boiler. Notify your gas
supply utility or LPG supplier.
15 to 25 mbar
25 to 45 mbar
Start the boiler.
above 25 mbar
above 45 mbar
Install a separate gas pressure governor
upstream of the system and regulate the
pre-charge pressure to 20 mbar for natu-
ral gas or 37 mbar for LPG. Notify your
gas supply utility or LPG supplier.
Setting the maximum output
You can limit the maximum output for
heating operation
. The limit is set via the
modulation range. The max. adjustable output is limited upwards by the boiler coding
card.
1.
Press
OK
and
å
simultaneously
for approx. 4 s.
2. "Service functions"
3. "Max. output"
4. "Change?"
Select
"Yes"
.
A value flashes on the display (e.g.
"85"). In the delivered condition, this
value represents 100 % of rated out-
put.
5.
Set the required value.
Commissioning, inspection, maintenance
Further details regarding the individual steps
(cont.)
5412 755 GB