Vitorond 200, VD2 Series 320 to 1080 Installation
5285 429 - 03
32
Enclosure
Boiler Control Installation
(continued)
6. Remove two plugs located on the back of the boiler
control housing using a flathead screw driver.
Mount control housing on the side panel.
7. Secure control housing using two supplied screws.
8. Run capillaries and boiler temperature sensor through
22 mm opening on side panel and insert them into
the sensor well as far as possible.
IMPORTANT
During installation and orientation of all cabling and
capillaries, ensure placement away from high heat sources
such as the vent, the chimney, or supply/return piping.
For electrical and boiler control connections,
see Installation Instructions of boiler control.
1. Mount top panel via hooks into side panels.
2. Attach mid top panels (models VD2-500 and up)
with hook to side panels (not shown).
3. Secure rear of top panels with hooks to side panels
and tighten to rear panels with B 3.5 x 9.5 sheet
metal screws.
4. Fasten brackets to rear panel, using sheet metal
screws.
5. Mount Vitorond 200 name plate to front panel as
shown.
Enclosure Installation
B 3.9 x 9.5
B 3.9 x 9.5
B 3.9 x 9.5