67
"Solar"
(on the boiler, HKK PCB)
■
"Pump On"
■
"Valve Open"
■
"Valve Close"
Calibrating the O
2
probe (Lambda probe)
The probe calibration required when replacing the
Lambda probe can only be performed manually.
For calibrating the Lambda probe, see "Maintenance".
Filling the vacuum module
Available if a charging scheme with vacuum module
was selected.
Press the following keys:
1.
|
/
~
for
"Yes"
.
Suction turbine starts automatically after
pressing
d
.
Terminating the commissioning sequence
Press the following buttons:
1.
|
/
~
for
"Yes"
or
" No"
.
"Yes"
to complete the commissioning
sequence.
The display changes to the standard menu.
"No"
to restart commissioning.
2.
d
to confirm.
Displaying the menu structure
If you exit the commissioning sequence by pressing
"
å
"
, the structure of the commissioning menu is dis-
played. Pressing
"
å
"
switches to the standard
menu.
Setting supply times for the vacuum system
You can individually set specific times during which
you do
not
want fuel to be supplied.
Operating instructions
Matching the control unit to the heating system
The control unit must be matched to the system equip-
ment level. Various system components are recog-
nised automatically by the control unit and the relevant
codes are set automatically.
Check all addresses in
Code 1
.
To select the addresses that have to be changed, see
chapter "Code 1".
Further setting options are listed in Code 2.
Setting the heating curves
The heating curves represent the relationship between
the outside temperature and the flow temperature.
To put it simply: The lower the outside temperature, the
higher the flow temperature.
Commissioning, inspection, maintenance
Commissioning the heating system
(cont.)
5679249