22
7602050
FIG.18
FIG.17
FIG.16
2.13-
Fit the limit switch and over-run microswitch
to
the bottom of the track only
(Fig. 17). Do not tighten
the grub screws at this time.
NOTE:
The shorter (square limit switch) must be fitted
in the top channel – failure to do this correctly could
damage the lift.
2.14-
Fit the bottom end cap to the track as shown in
(Fig. 18), ensuring that the power supply cable is fed
through the channel provided so that it exits the track
on the WALL side.
2.15-
Tighten the grub screws to secure the end cap
to the track.
NOTE:
The grub screws on the end cap should not be
over tightened.
2.16-
Now slide the limit switch and over-run microswitch
stop so that they sit against the positioning extensions
of the end cap and then tighten the grub screws as
shown in (Fig. 18).
3) FEET POSITIONING
Items required:
None
Tools required:
13mm Spanner
13mm Socket
3.1-
Slide the track to the stair side chosen to position
the feet.
The feet should be positioned so that they are touching
the upright as shown in (Fig. 19).
NOTE:
If the stringer does not extend to the tread, i.e.
it overhangs the staircase, use a plumb line to mark a
position on the stairs. The feet should all be positioned
in this way.
3.2-
With the end of the track positioned so that it is just
touching the floor ensure that the feet are still positioned
on the stair treads as previously described (Fig.9), i.e:
a-
The top foot should be positioned on the last tread.
b-
The middle foot should be positioned immediately
above the spliced joint.
c-
The bottom foot should be positioned on the first
tread.
3.3-
Tighten the bolts on the feet as shown in (Fig. 20).
FIG.15