95x Series Operating Manual - May 17, 2022
Page
136
of
155
1
st
checked value is rms leakage current
No minimum 1
st
leakage current limit
5mArms maximum 1
st
leakage current limit
No 2
nd
checked limit (so following two fields are <EMPTY>)
No arc detection (so following field is also <EMPTY>)
Fast discharge
Abort test sequence if fails
HV Terminal used (AC-30 not used or not installed) since both fields 17 and 18 are missing
DUT is isolated since both fields 17 and 18 are missing
DCEZ CONFIGURATION FIELDS
Field # Field Format Value
1
<STRING>
DCEZ
2
<NR3>
Test Voltage (in V)
3
<NR3>
Ramp Time (in seconds)
4
<NR3>
Dwell time (in seconds)
<EMPTY>
Step is to be user terminated
5
<NR3>
Minimum Leakage Limit (in A)
6
<NR3>
Maximum Leakage Limit (in A)
7
<STRING>
ABORT - Abort on failure
CONT - Continue on failure
8
<EMPTY>
Load is not grounded
<MISSING>
<STRING>
GND : Load is grounded (only valid if option HSS or HSS-2 is fitted)
ISO : Load is not grounded
Example
–
ADD,DCEZ,1000.0,1.5,60.0,0.0,0.005,ABORT
Configures the following (in order)
–
A DCez type test step
1000V test voltage
1.5 second ramp time
60 second dwell time
No minimum leakage current limit
5mA maximum leakage current limit
Abort test sequence if fails
DUT is isolated since field 8 is missing
DCW CONFIGURATION FIELDS
Field # Field Format Description
1
<STRING>
DCW
2
<NR3>
Test Voltage (in V)
3
<NR3>
Breakdown Limit (in A)
4
<NR3>
Ramp Time (in seconds)