2.6 - L
EVELING
Installation manual myReflow
C
HAPTER
2
7
2.6
L
EVELING
After the machine is placed on its location and the cover is opened, the next steps should be fol-
lowed.
F
IGURE
2.8
A
DJUSTING
LEVEL
F
IGURE
2.9
L
EVELING
1.
Adjust the threaded feet of the machine until it stands perfectly in both X and Y direction.
A spirit level should be placed on the frame for checking the X direction. For the Y-
direction the spirit level should be placed on both conveyorbars.
2.
When machine is leveled, tighten the nuts (A). See
After this procedure the machine is mechanically correct installed.
36 mm open
17 mm open
A
B
ended spanner
ended spanner
57-139mm
X- level
TOPVIEW
SIDEVIEW
Y- level
spirit-level
Summary of Contents for 42284
Page 4: ...iv...
Page 8: ......
Page 24: ...INSTALLATION 8 CHAPTER 2 2 7 INSTALLATION SHEETS AND REQUIREMENTS see next pages...
Page 25: ...1 Installation sheets 10 Positions Front View MR820A myReflow 7038 VERSION November 2009...
Page 26: ...2 Installation sheets myReflow 7038 VERSION November 2009 Top View 10 Positions MR820A...
Page 33: ...9 Installation sheets myReflow 7038 VERSION November 2009 Side View...