background image

 

26

Noisiness 

Propeller breakup 

Small lesions: reparation allowed only 
for experienced person. Otherwise 
substitution.. 

Components' breakup (es. muffler, 
bearings, bracket) 

Check the motor. Don't use the motor 
up to the problem has not been 
identified and resolved. 

Soundproofing material worn out 

Replace it 

Gasket connection exhaust/silencer 

Replace it 

Model Easy100: belt dirty, low tension or 
worn out 

Cleaning, right tension or replace it  

Model Fly100evo:

 

lack of oil in the 

reduction drive 

Replace oilseals and 20cc of oil 

Model Fly100evo: bearings or gearings 
worn out 

Replace it 

Model Fly100evo: clutch worn out 

Replace mass of the clutch 

 

Sudden turning off 

Aspiration of air from the circuit tank-
bulb-filter-carburetor 

Check the junctions or replace the aged 
pipeline or bulb 

The spark-plug is worn out or defective 

Substitution 

The spark-plug has soot in the electrode 

Clean it with an iron brush or replace it. 

The cap of the spark-plug is not well 
installed with the cable 

Checkup or replace the cap. 

The electric plant 

Check there are no cables or wiring worn 
out or open. 
Check the correct installation. 

The ignition coil or the contact breaker 
has a problem 

Replace it 

Overheating 

See section above: overheating 

Carburetor problem 

Get off and inspect 

 

Strongly smokiness from the silencer 

The gasoline in the tank has a wrong  
percentage of oil 

Void the tank and replace it 

Wrong carburation 

Restore the standard carburation 

Soundproofing material worn out 

Replace it 

 

Leaking of oil 

Connection cylinder to exhust pipe 

Replace the two o-rings 

Connection exhaust pipe to silencer 

Replace gasket 

Silencer 

Clean the silencer with thinner, replace 
the soundproofing, add sealing paste on 
the junctions 

Reduction drive Fly100evo 

Replace oilseals 

Crankcase, oilseals, o-rings or gaskets 

Dismount, clean the plains, replace the 
worn out components, add sealing paste 
where necessary.  

 

Summary of Contents for Easy100

Page 1: ...pe vittorazi motors Sito web www vittorazi com Owner s manual Last update October 2007 Model Vittorazi Easy100 Model Vittorazi Fly100evo All the indications writes in the charts of this manual will be...

Page 2: ...g new horizons 6 0 Specifications and technical data 7 0 Maintenance 7 1 Ignition coil and spark plug 7 2 Check and cleaning carburetor 7 3 Reed valve 7 4 Gaskets 7 5 Exhaust silencer 7 6 Rubber mount...

Page 3: ...he claim the serial number XXXX of the motor that you find under the system carburetor some photos if you think will be necessary You find the direct contacts of the factory in the first and in the la...

Page 4: ...on the ground take off landing watch out that nobody draws near to the propeller in rotation A good safety distance is 50 meters for all directions of projection of the propeller and 20 meters for th...

Page 5: ...completely Now gently screw the bolts up to the end Be sure that the bolt are proper for the propeller therefore the threads of the bolts are inserted at least 10mm in the hub Now to tighten the bolt...

Page 6: ...ember measure material of the propeller and model of the motor The use of a not conform propeller or the use of a propeller Vittorazi united to a wrong reduction ratio brings immediately end of the wa...

Page 7: ...nk of the aircraft filter the mixture Be sure that the tank for the transport gasoline filter and funnel is perfectly always clean We advise only oil of good quality certified and full synthetic no oi...

Page 8: ...th a minimum of throttle If the circuit of fuel is on pressure and the motor is warm it won t be necessary to make pressure on the primer bulb and valve Always watch out for the propeller during the s...

Page 9: ...assemblage and the optimal carburetor setting Chart 4 5 Carburetor setting Vittorazi Easy100 Vittorazi Fly100evo Screw L from 1 4 to 1 3 of turn from 1 4 to 1 3 of turn Screw H from 1 1 8 to 1 1 4 of...

Page 10: ...y of gasoline that arrive to the motor is poor therefore the opening of the screw is lower in comparison to the indications of the chart will probably occur breakups as seizures overheatings fusions o...

Page 11: ...skilled person The chapter or paragraph is reserved to the manufacture dealer or center assistance Vittorazi If you are our collaborators we invite you to write to our e mail address and get the integ...

Page 12: ...motor won t be optimal with these regulations but you will get a good break in and a guarantee of duration for the organs of the motor The first starting of the motor must be made to the ground on sh...

Page 13: ...lug with the same type and gradation at the end of the break in because the quantity of fuel and oil in excess could have decreases notably the duration of it Chart 5 1 NORMAL OPERATION Vittorazi Easy...

Page 14: ...atio 1 3 3 1 3 65 1 4 Clutch centrifugal adjustable Max speed 9 400 9 600 RPM Max speed 9 400 9 600 RPM Thrust 58 kg with prop 125cm Pilot up to 90 100kg Thrust 58 kg with prop 125cm Pilot up to 90 10...

Page 15: ...ar The spark plug can last years or to stop working after some minutes if the shrewdness are not followed We advise not to leave the motor idling for some minutes and accordingly to flood it We advise...

Page 16: ...00 hours of use or once for year After some months the membranes of an unused motor can become stiff to contact with the gasoline or can bend in the normal use losing their peculiarity to oscillate an...

Page 17: ...assemblage of the new soundproofing material Add as denoted in the figure 7 5 1 and 7 5 2 a sealing paste resistant to high temperatures on the points of junction fix two new rivets in the original p...

Page 18: ...earranged provided of patience manually in the original position In the figure 5 freed the pulley is shown the spooling spring Assemblage add grease to the spooling spring and the pivot where slides t...

Page 19: ...s You remember the sequence and the position of all the components of the starter Once assembled pulley cammes springs and cover you insert the screw and verify the sliding of the system You load thro...

Page 20: ...he bearing of the pinion the condition of usury of the belt lasted average of 100 150 hours A last important shrewdness consists in the measurement of the housing where lodges the bearing of the pinio...

Page 21: ...eel and ignition timing 7 14 Crankshaft crankcase bearings The chapter or paragraph is reserved to the manufacture dealer or center assistance Vittorazi If you are our collaborators we invite you to w...

Page 22: ...Reed valve Checkup Substitution Soundproofing material silencer Optional substitution Necessary substitution O ring exhaust Substitution Spark plug Substitution Gaskets Substitution Piston ring Substi...

Page 23: ...m 9 10 Nm Screws or nuts of 8mm 25 27 Nm Screws carbon propeller of 6mms 4 5 Nm 1 Kgm 9 81 Nm Tools of measurement Centesimal caliper Feeler from 0 05 to 1 00 mms Torque wrench scale 2 10 Nm Scale 8 6...

Page 24: ...e motor with the starting or handly Dry the spark plug The spark plug has soot in the electrode Clean it with an iron brush or replace it The cap of the spark plug is not well installed with the cable...

Page 25: ...ater or other liquids it is dirty Void the tank and replace it The gasoline in the tank has a wrong percentage of oil Void the tank and replace it Aspiration of air from the circuit tank bulb filter c...

Page 26: ...plug has soot in the electrode Clean it with an iron brush or replace it The cap of the spark plug is not well installed with the cable Checkup or replace the cap The electric plant Check there are n...

Page 27: ...ity of the motor every motor before being delivered is submitted to a test of verification a simulation of flight made on the thrust bench of about 15 minutes The present warranty remains in vigor for...

Page 28: ...other causes that can influence the performances of the motor an improper use or from maltreatment of the motor wrong regulations or setting omission of generic controls missed cleaning of the carbure...