05TA Service Manual
SERVICE OPERATIONS
7/24/13
9-22
Water Tank Removal.
1. Turn off and lock out power to the machine.
2. Turn off water supply and disconnect lines from the tank.
3. Drain the tank and disconnect pump suction tube and drain line tubing and water lines.
4. Disconnect the ice discharge chute.
5. Loosen water tank clamp that couples the plastic tank to the cutter housing assembly.
6. The tank can then be removed to the side of the machine.
Cutter and Bearing Removal/Installation.
Refer to FIGURES 9-16, 9-17,& 9-18A for parts
identification and location
1. Turn off and lock out power to the machine.
2. Remove the cutter motor from the reducer.
3. Remove the water tank assembly and then the cutter assembly.
4. With a 1/4” or slightly smaller punch, reach in through the ice discharge opening, drive the spiral
pin out of the disc hub and cutter shaft, and push or drive the disc off the shaft.
5. Lift the cutter assembly out of the bearing surface of the cutter. The surface should be smooth
and free from nicks or burrs.
6. Inspect the bearing for wear. There should be no side movement between the shaft and bearing
and the bearing thrust flange should be no thinner than 3/16” (it is 1/4” thickness new).
7. Before removing the bearing, reference mark the location of the bearing support on the side of
the tank.
8. Loosen and remove the three cap screws from the bearing support ends and lift the support out of
the water tank.
9. Drive the 3/16” x 1/2” pin located in the side of the support hub in and through the bearing wall.
10. Now the bearing can be pressed or driven out of the support hub.
11. Try the new bearing on the cutter shaft to make sure it turns easily.
12. Press or drive the new bearing into the hub. Be careful not damage the bearing surfaces (the old
bearing may be used as a driver).
13. Drill a 3/16” hole through the bearing wall, using the original hub hole as a pilot. Insert and
drive the 3/16” pin flush with the outside of the hub, making sure the pin doesn’t extend beyond
the inner surface of the bearing.
14. Slide the new bearing and support onto the cutter shaft to make sure it spins freely. If it is tight,
ream the bearing inner surface slightly until it turns free.
15. Install the bearing support in the tank, using the reference marks as a guide.
16. Slide the cutter and shaft into the bearing and check the cutter alignment. By laying a straight
edge across the tank top flange, there should be 0” to 1/16” clearance between the rim of the
cutter and the top of the tank flange. Loosen the bearing support cap screws and drive the
support arms up or down for the proper alignment.
17. Tighten the support screws securely and finish assembly of the cutter and cutter disc.
18. Install the tank and other parts, reversing the procedure of removal.
Summary of Contents for P118F/HE100
Page 4: ...Vogt Tube Ice Machines Installation Service Manual and Parts Catalog 12A4171M06 05TA Model ...
Page 10: ...05TA Service Manual TABLE OF CONTENTS vi ...
Page 20: ...05TA Service Manual INTRODUCTION 7 19 13 1 10 ...
Page 40: ...05TA Service Manual INSTALLING YOUR TUBE ICE MACHINE 3 7 14 3 18 BLANK PAGE ...
Page 50: ...5 6 5TA Service Manual START UP AND OPERATION 7 19 13 Blank page ...
Page 106: ...05TA Service Manual SERVICE OPERATIONS 3 10 14 9 28 Blank ...
Page 114: ...Blank page ...
Page 115: ...05TA Service Manual TABLES CHARTS 3 10 14 11 1 11 Tables Charts ...