Solar Schematic 

 

 

 

 

 

 

 

230V supply from solar 
controller to Solar Pump  
 
230V supply to Solar 
Pump 
 
Please note that the 
power to the Solar Pump 
from the solar controller 
must pass through solar 
thermostat 

 

Solar Thermal cut off 

 

AQUAFLOW FAULT FINDING GUIDE 

FAULT 

POSSIBLE CAUSE 

REMEDY 

No water flow from hot taps 

1.

 

Mains supply off. 

2.

 

Strainer blocked. 

 
 
 
3.      Cold water inlet Pressure        
         Reducing Valve incorrectly        
         fitted. 

1.

 

Check and open stopcock. 

2.

 

Turn off water supply. Remove 
strainer and clean. (See Pressure 
Reducing Valve page 6 Installation 
Manual) 

3.

 

Check and refit as required.(see item 
3 page 5 of installation manual) 

Water from hot taps is cold. 

1.

 

Immersion heaters not 
switched on. 

2.

 

Immersion heater thermal cut-
out has operated. 

 
 
3.

 

Programmer set to central 
heating or not switched on. 

4.

 

Boiler not working. 

 
 
5.

 

Cylinder thermal cut-out has 
operated.  

6.

 

Motorised valve not operating 
correctly. 

1.

 

Check and switch on. 

 
2.      Check and reset button. (See   
         thermostat diagram page      
         9 and safety cut-out on page 4 of         
         Installation manual). 
3.      Check and set to hot water. 
 
4.

 

Check boiler operation. If fault 
suspected consult installer or boiler     

         manufacturer. 
5.

 

As at No. 2. 

 
6.

 

Check wiring and / or plumbing 
connections to motorized valve. (See 
pages 8 or 10 of the installation 
manual). 

Summary of Contents for AquaFlow

Page 1: ...ions THESE INSTRUCTIONS TO BE RETAINED BY USER Vok ra is a licensed member of the Benchmark scheme which aims to improve the standards of installation and commissioning of domestic hot water systems i...

Page 2: ...nsporting or supporting of a load including the lifting putting down pushing pulling carrying or moving thereof by hand or bodily force The Regulations set no specific requirements such as weight limi...

Page 3: ...ock 250445 5 Temperature and Pressure Relief Valve 550803 14 Cable Entry 6 Tundish 219002 15 Electrical Box 7 Immersion Heater 71255 16 Tee Piece 250006 7A Thermostat Immersion Heater Thermostat Cylin...

Page 4: ...tting MI Drain Cock 250440 4 Check and Expansion Valve 510505 13 Elbow Drain Cock 250445 5 Temperature and Pressure Relief Valve 550803 14 Cable Entry 6 Tundish 219002 15 Electrical Box 7 7A Immersion...

Page 5: ...hose to the 1 2 outlet of the expansion valve 4 and the horizontal outlet of the tee piece see 5 above Discard compression nut ring 11 If a balanced mains pressure cold water supply is required to a...

Page 6: ...sion vessel to the cylinder as shown in the diagram below The vessel should be charged pressurised to the same pressure as the PRV Pressure Reducing Valve Solar Primaries 20 The Solar flow and return...

Page 7: ...oid damage to element Isolate boiler from Aquaflow unit Turn off the cold water supply valve Open hot water tap Open drain 13 The unit will drain SAFETY AND MAINTAINANCE Safety Cut out 1 The safety cu...

Page 8: ...of the body 4 The expansion valve should be either horizontal or upright if fitted inverted debris may be deposited on the seat and cause fouling of the seat when the valve operates Check direction of...

Page 9: ...Unscrew blue expansion relief headwork from valve body 3 Clean valve seat face and seating do not scratchordamageeithersealfaceorseating 4 Refit in reverse order Do not overtighten Expansion valve ca...

Page 10: ...t out is also incorporated within the thermostat and will operate at 85 C 3 C Should the safety cut out be brought into operation the motorised valve will operate and close down the primary flow to th...

Page 11: ...0161 620 6677 10 S Plan systems Refer to the wiring diagrams contained within the boiler installation instructions for the wiring of S Plan systems Connect the cylinder thermostat as shown in the dia...

Page 12: ...ng Layout Refer to the wiring diagrams contained within the boiler installation instructions for the wiring of Y Plan systems Connect the cylinder thermostat as shown in the diagram below NOTE A10wayj...

Page 13: ...Reducing Valve page 6 Installation Manual 3 Check and refit as required see item 3 page 5 of installation manual Water from hot taps is cold 1 Immersion heaters not switched on 2 Immersion heater the...

Page 14: ...check thermal controls replace if faulty Contact a competent person Continuous water discharge 1 Cold water inlet Pressure Reducing Valve not working 2 Temperature and pressure relief valve faulty 3 E...

Page 15: ...Supplied By www heating spares co Tel 0161 620 6677 14...

Page 16: ...Supplied By www heating spares co Tel 0161 620 6677 15...

Page 17: ...Supplied By www heating spares co Tel 0161 620 6677 16 Notes...

Page 18: ...umber of discharges such as in blocksofflats thenumberservedshouldbelimitedtonotmorethan 6 systems so that any installation discharging can be traced reasonably easily The single common dischargepipes...

Page 19: ...L2 1HG enquiries vokera co uk www vokera co uk www vokera ie Sales General Enquires T 0844 391 099 F 0844 391 0998 Vok ra Ireland West Court Callan Co Kilkenny T 056 7755057 F 056 7755060 Vok ra Limit...

Reviews: