ENGAGEMENT OF ITA WITH RECEIVER
Listed below are the required steps for proper engagement of the ITA to the receiver.
•
Prior to engaging an ITA with the receiver for the first time, it is good practice to check that all modules (ITA and receiver) have
been installed properly. This involves inspection of module ends - ensuring even height relative to one-another. While checking this,
the user should also verify the positioning of the modules. Pin 1 should always be at the top of both ITA and receiver modules. It is
crucial for all modules to be installed properly. Improper installation will cause damage to modules, and possibly to the ITA and/or
receiver. All ITA modules must match receiver modules. Upon engagement, ITA modules will mate with their respective receiver
modules.
•
Following inspection, the ITA is ready for engagement with the receiver. The receiver should be checked one last time for any
foreign objects that may hinder engagement. With the ITA in the upright position and the receiver handle open, align guide pins
with bushings on the ITA and mate.
•
The handle may now be moved to the upright/ closed position to engage contacts.
CAUTION
• When engaging the ITA with the receiver, caution must be taken to ensure
that the ITA is parallel with the receiver upon engagement and that the ITA
rollers are engaged at the same time.
• To prevent potential injury, care should be taken to avoid wrapping fingers
around the engagement handle.
• All power supplies for the system should be properly disconnected prior to
handling. When engaging, be sure that all foreign objects are removed from
the system.
2
G6 ITA •
PART # 410 104 273, 410 104 331
G6 RCV •
PART # 310 104 318
G10 ITA •
PART # 410 104 272, 410 104 375
G10 RCV • PART # 310 104 317
In the event of difficulties with
engagement, such as improper
alignment of modules or the ITA, a
trained VPC technician should be
notified immediately to avoid any
damage to the system.