Moisture condensed out of the airstream on cooling or dehumidifying coils should be drained out from the unit 

in order to sustain the proper use of the air handling unit and the ductwork system. Following precautions should 

be observed in piping of condensate drain lines.

Connection  of  electric  AHU  elements  should  be  carried  out  by  qualified  personnel  and  should  be  done  in 

accordance with any standards and regulations being in force in a country where the unit is installed. Cross- 

section and type of cables (e.g. shielded cable) feeding individual functional segments should be selected 

basing on nominal current and specific operation conditions (e.g. ambient temperature, way of cabling, distance 

from the power supply).
All connections which are field made by a contractor shall be conducted in accordance with delivered together 

with ahu diagrams.
Before starting connecting power supply, check conformity of the voltage and frequency of a supply network 

with the data shown on the device's rating plate. Permissible fluctuation of the supply voltage and its frequency 

to the values shown on the rating plate is ±5%. If discrepancy exists, the device cannot be connected.

CONDENSATE DRAIN LINES

ELECTRIC CONNECTIONS

3.6.3

3.6.4

The bore size of the pan outlet connection should not be less than the pipe connection of the 

drain pan.

A union or pipe coupling should be fitted at the drain pan pipe connections to permit easy 

disconnection for cleaning any dirt sediments.

The siphon (for positive and negative pressure applications) which is sent separately in the unit 

should be assembled according to the installation instructions given below.

!

»

 

Drainage U-trap connection

 

Negative pressure

H= [(-)Pa / 10] + X

PVS 3-6 

-> X =50 mm

PVS 6-6 - 15-15 

-> X= 40 mm

PVS 15-18 – 37-40  -> X = 30 mm

 

Positive pressure

H= (Pa / 10) 

X= (1,5 x H) + 40

R= X + 75 

AB= R - A

Z =  80 mm   

-> A =  40 mm

Z = 120 mm   

-> A =  60 mm

Z =200 mm   

-> A = 140 mm

Summary of Contents for ventus PRO 2022

Page 1: ...VENTUS PRO AIR HANDLING UNITS OPERATION INSTALLATION AND MAINTENANCE MANUAL PRO 2022 OIMM VENTUS PRO Ver 1 0 0 31 05 2022...

Page 2: ...FOR AHU ASSEMBLY CARRIED OUT BY VTS AUTHORIZED SERVICE 6 INSTALLATION 7 CONNECTIONS 9 DUCTED OUTLE CONNECTIONS 10 PIPING CONNECTIONS 11 CONDENSATE DRAIN LINES 13 ELECTRIC CONNECTIONS 13 SETTING UP OF...

Page 3: ...so as to prevent the device from being started accidentally Before connecting the electric power supply check the compliance of the mains voltage and frequency with the data on the name plate of the d...

Page 4: ...th AHU subassemblies transport of the packages to the assembly location and transport of AHU blocks and elements to the assembly location should be carried out using special equipment and qualified st...

Page 5: ...e from 5 to 35 C In case of outdoor assembly the procedure can be carried out in precipitation free conditions It is acceptable to start the assembly provided that all safety and security requirements...

Page 6: ...safe environment for the installation crew The following should be provided availability of individual AHU elements or pallets including packages on the assembly place of a particular AHU Ensured tran...

Page 7: ...ure that access routes are adequate for both size and weight of the unit sections Air handling unit installation areas should also be checked There should be sufficient space around the unit for servi...

Page 8: ...installed in the AHU sections where negative pressure occurs Drain siphons or siphon parts are not supplied as standard delivery There is no need to apply drain siphons in section with overpressure I...

Page 9: ...ted to the AHU with the flexible connections optional accessory which suppress vibrations of the unit and level the coaxial deflection of the duct and the AHU outlets Flexible connections are equipped...

Page 10: ...d prior to the reducing section To achieve ideal conditions the length of parallel ducting in both cases should be equal to 8 impeller diameters However parallel ducting of considerably shorter length...

Page 11: ...ves any air in the system into the upper part of the coil where a manual air release valve should be fitted PIPING CONNECTIONS 3 6 2 The diameter of the connection and the type of connection of the ex...

Page 12: ...12 OIMM VENTUS PRO COIL CONNECTION RULES COIL INSTALLATION HYDRONIC COILS COIL INSTALLATION STEAM COILS Hydronic Steam...

Page 13: ...d together with ahu diagrams Before starting connecting power supply check conformity of the voltage and frequency of a supply network with the data shown on the device s rating plate Permissible fluc...

Page 14: ...efault motors with their own cooling system and with fans built into a shaft Supply cabling must be led to the fan s motor via rubber passes located in the back panel of the AHU casing One should conn...

Page 15: ...s in accordance with guidelines outlined in the operation and maintenance manual of the frequency converter Before putting into service and after long time of storage or standstill the resistance of i...

Page 16: ...e marked U V W and the neutral terminal N please check data on the rating plate The voltage marked on the rating plate must be in agreement with the mains voltage the terminal board is normally equipp...

Page 17: ...h water heat exchangers heaters coolers glycol recovery air damper s actuators of supply units should be equipped with a return spring ensuring its spontaneous closure in case of power cut SETTING UP...

Page 18: ...d be taken in to account System layout should take into consideration of possible coil withdrawal It is recommended that the water flow is shut off when the fan is switched off To avoid the overheatin...

Page 19: ...tarters controls overload protecting devices interlocks etc should be provided as required See page 34 After the start up check that direction of rotation of the fan is correct The electric heater sho...

Page 20: ...nits must not be used for handling of flammable gases Spark proof versions of rotating parts fans motors etc must be selected for this kind of applications so air handling unit manufacturer should be...

Page 21: ...represent a danger suitable guards can be installed drive guards Safety guards should be used when drive systems are accessible by the personnel limit switch Cuts off the power supply of the fan moto...

Page 22: ...ensure all panels if removed during installation are in position and all service doors are closed ensure that minimum water level is maintained in the humidifier On the downstream or pressure side of...

Page 23: ...rical supply secure fan impeller if there is a possibility of windmilling Check carefully for the cause of the problem and correct as necessary After ensuring that there is not any problem no leaks be...

Page 24: ...less electric supply has been locked out and the impeller has been secured Before the maintenance operation the safety precautions should be taken by locking out the main and maintenance switch and pr...

Page 25: ...AR Check the filter frame for proper sealing Replace synthetic filter media in panel filters Check the controls and operation of automatic roll filters Check the coils and fins Wash with water spray i...

Page 26: ...cracks on the copper tubes by oxyacetylene welding Check with water if the welding is successful or not After cleaning the coil drain should be checked and the siphon should be cleaned Condition of th...

Page 27: ...the filters can be taken out by pulling aside Synthetic bag filter can be cleaned by vacuumed or compressed air besides can be washed with the sensitive detergent and warm water Humidifier should be c...

Page 28: ...quate It goes without question however that like all Rules of thumb some judgement is necessary on the part of person doing the adjusting A belt should be just tight enough to avoid slippage Before lo...

Page 29: ...the housing Relubrication interval depends on the fan speed and bearing internal diameter and is calculated by the following formula t 10 x 14x106 n x d 4 x d where t relubrication interval h n fan sp...

Page 30: ...se be removed from the bearing arrangement and replaced by fresh grease The 6 months limit represents a very rough guideline recommendation and may be adapted to particular applications By adding smal...

Page 31: ...s recommended to contact the unit manufacturer System checklist A systematic check of items listed below may identify the problem See that a impeller rotation is correct b pulley are aligned c belts a...

Page 32: ...ings Noise from bearings Loose on support Tighten bearings Loose on shaft Tighten shaft Bearings worn or damaged Change bearings Bearings need lubrication Lubricate bearings Foreign material inside be...

Page 33: ...tlet duct system is not completed Check access doors and duct joints Seal leaks Complete duct system HIGH AIR FLOW Ducts are oversized or duct resistance overestimated Close balancing dampers or slow...

Page 34: ...w Oversized coil or compressor ELECTRONIC STEAM HUMIDIFIER No humidifying Electronic power failure Power is not reaching elements or control valve Thermostatic gear fault Heater elements faulty Safety...

Reviews: