Sending the ‚Confirmation of Readiness for Assembly’ is indispensable to start the assembly 

process by Authorized Service. If real conditions do not correspond to the information given 

in confirmation VTS shall be entitled to demand reimbursement of the costs incurred due to 

service stoppages or additional actions performed by the service on site.

!

CONDITIONS FOR AHU ASSEMBLY CARRIED OUT BY VTS AUTHORIZED SERVICE

3.4

FOUNDATION, ASSEMBLY, CONNECTION  

OF UNIT-RELATED SYSTEMS

The following conditions apply to the delivery of AHUs in packages and orders for the assembly of devices on 

site by VTS.

»

 

PREPARATION FOR ASSEMMBLING

Before starting AHU assembly VTS shall send to customer a document entitled ‚Confirmation of Readiness for 

Assembly’ (enclosure no 1).
The  document  contains  important  information  about  the  installation  process.  Having  satisfied  conditions 

specified in it the document should be signed in the indicated place and sent to the specified VTS office.

»

 

ASSEMBLY SITE

An assembly place should meet the following conditions:

• 

The right surface – the surface should be hard, dry, protected from atmospheric influence, and damage 

resistant (placement of the unit, installation works).

• 

The required installation place area: 

- Width of the unit + 4 meters (two meters on each side of the unit), 

- Length of the unit + 4 meters (two meters on each side of the unit)

• 

The 230V AC power supply should not be located further than 20m from the installation place which should 

be properly lit.

• 

The place of installation shall provide a safe environment for the installation crew.

• 

The following should be provided:  

- availability of individual AHU elements or pallets including packages on the assembly place of a 

particular AHU. Ensured transport of AHU elements and AHU blocks to the place of installation, 

- possibility of service entering the site and starting assembly immediately after their arrival, 

- making the Warranty Card and Delivery documents supplied with a particular AHU available to the service

»

 

ASSEMBLY COMPLETION

After the installation is completed the service is obliged to:

• 

notify the client’s representative about the fact of finishing assembly,

If a unit operates with the low inlet temperature of the air, it is recommended to use the mixture of the glycol (up 

to 45%) as the heating medium. All installation pipes of the water heating, condensate drying, hydraulic valves 

should be well isolated. 
It is recommended to use the pre-heater before the heat recovery section.
The air damper actuators should be protected from the atmospheric conditions. 
If the outdoor temperature is lower than -20°C, the air dampers actuators must be equipped with heating elements. 
All equipment and components operating outside the unit must have the required IP.
Units, periodically stopped during periods of low outdoor temperatures, require special attention.
A unit shall be equipped with control system, that supports the flow of the liquid through water heaters to prevent 

it from freezing during AHU downtime. 
If it is possible that temperature in the fan section fall below -30°C or lower, the sections should be equipped with 

an internal heating system to ensure reliable start of the motors after shutdown and downtime.

Summary of Contents for ventus PRO 2022

Page 1: ...VENTUS PRO AIR HANDLING UNITS OPERATION INSTALLATION AND MAINTENANCE MANUAL PRO 2022 OIMM VENTUS PRO Ver 1 0 0 31 05 2022...

Page 2: ...FOR AHU ASSEMBLY CARRIED OUT BY VTS AUTHORIZED SERVICE 6 INSTALLATION 7 CONNECTIONS 9 DUCTED OUTLE CONNECTIONS 10 PIPING CONNECTIONS 11 CONDENSATE DRAIN LINES 13 ELECTRIC CONNECTIONS 13 SETTING UP OF...

Page 3: ...so as to prevent the device from being started accidentally Before connecting the electric power supply check the compliance of the mains voltage and frequency with the data on the name plate of the d...

Page 4: ...th AHU subassemblies transport of the packages to the assembly location and transport of AHU blocks and elements to the assembly location should be carried out using special equipment and qualified st...

Page 5: ...e from 5 to 35 C In case of outdoor assembly the procedure can be carried out in precipitation free conditions It is acceptable to start the assembly provided that all safety and security requirements...

Page 6: ...safe environment for the installation crew The following should be provided availability of individual AHU elements or pallets including packages on the assembly place of a particular AHU Ensured tran...

Page 7: ...ure that access routes are adequate for both size and weight of the unit sections Air handling unit installation areas should also be checked There should be sufficient space around the unit for servi...

Page 8: ...installed in the AHU sections where negative pressure occurs Drain siphons or siphon parts are not supplied as standard delivery There is no need to apply drain siphons in section with overpressure I...

Page 9: ...ted to the AHU with the flexible connections optional accessory which suppress vibrations of the unit and level the coaxial deflection of the duct and the AHU outlets Flexible connections are equipped...

Page 10: ...d prior to the reducing section To achieve ideal conditions the length of parallel ducting in both cases should be equal to 8 impeller diameters However parallel ducting of considerably shorter length...

Page 11: ...ves any air in the system into the upper part of the coil where a manual air release valve should be fitted PIPING CONNECTIONS 3 6 2 The diameter of the connection and the type of connection of the ex...

Page 12: ...12 OIMM VENTUS PRO COIL CONNECTION RULES COIL INSTALLATION HYDRONIC COILS COIL INSTALLATION STEAM COILS Hydronic Steam...

Page 13: ...d together with ahu diagrams Before starting connecting power supply check conformity of the voltage and frequency of a supply network with the data shown on the device s rating plate Permissible fluc...

Page 14: ...efault motors with their own cooling system and with fans built into a shaft Supply cabling must be led to the fan s motor via rubber passes located in the back panel of the AHU casing One should conn...

Page 15: ...s in accordance with guidelines outlined in the operation and maintenance manual of the frequency converter Before putting into service and after long time of storage or standstill the resistance of i...

Page 16: ...e marked U V W and the neutral terminal N please check data on the rating plate The voltage marked on the rating plate must be in agreement with the mains voltage the terminal board is normally equipp...

Page 17: ...h water heat exchangers heaters coolers glycol recovery air damper s actuators of supply units should be equipped with a return spring ensuring its spontaneous closure in case of power cut SETTING UP...

Page 18: ...d be taken in to account System layout should take into consideration of possible coil withdrawal It is recommended that the water flow is shut off when the fan is switched off To avoid the overheatin...

Page 19: ...tarters controls overload protecting devices interlocks etc should be provided as required See page 34 After the start up check that direction of rotation of the fan is correct The electric heater sho...

Page 20: ...nits must not be used for handling of flammable gases Spark proof versions of rotating parts fans motors etc must be selected for this kind of applications so air handling unit manufacturer should be...

Page 21: ...represent a danger suitable guards can be installed drive guards Safety guards should be used when drive systems are accessible by the personnel limit switch Cuts off the power supply of the fan moto...

Page 22: ...ensure all panels if removed during installation are in position and all service doors are closed ensure that minimum water level is maintained in the humidifier On the downstream or pressure side of...

Page 23: ...rical supply secure fan impeller if there is a possibility of windmilling Check carefully for the cause of the problem and correct as necessary After ensuring that there is not any problem no leaks be...

Page 24: ...less electric supply has been locked out and the impeller has been secured Before the maintenance operation the safety precautions should be taken by locking out the main and maintenance switch and pr...

Page 25: ...AR Check the filter frame for proper sealing Replace synthetic filter media in panel filters Check the controls and operation of automatic roll filters Check the coils and fins Wash with water spray i...

Page 26: ...cracks on the copper tubes by oxyacetylene welding Check with water if the welding is successful or not After cleaning the coil drain should be checked and the siphon should be cleaned Condition of th...

Page 27: ...the filters can be taken out by pulling aside Synthetic bag filter can be cleaned by vacuumed or compressed air besides can be washed with the sensitive detergent and warm water Humidifier should be c...

Page 28: ...quate It goes without question however that like all Rules of thumb some judgement is necessary on the part of person doing the adjusting A belt should be just tight enough to avoid slippage Before lo...

Page 29: ...the housing Relubrication interval depends on the fan speed and bearing internal diameter and is calculated by the following formula t 10 x 14x106 n x d 4 x d where t relubrication interval h n fan sp...

Page 30: ...se be removed from the bearing arrangement and replaced by fresh grease The 6 months limit represents a very rough guideline recommendation and may be adapted to particular applications By adding smal...

Page 31: ...s recommended to contact the unit manufacturer System checklist A systematic check of items listed below may identify the problem See that a impeller rotation is correct b pulley are aligned c belts a...

Page 32: ...ings Noise from bearings Loose on support Tighten bearings Loose on shaft Tighten shaft Bearings worn or damaged Change bearings Bearings need lubrication Lubricate bearings Foreign material inside be...

Page 33: ...tlet duct system is not completed Check access doors and duct joints Seal leaks Complete duct system HIGH AIR FLOW Ducts are oversized or duct resistance overestimated Close balancing dampers or slow...

Page 34: ...w Oversized coil or compressor ELECTRONIC STEAM HUMIDIFIER No humidifying Electronic power failure Power is not reaching elements or control valve Thermostatic gear fault Heater elements faulty Safety...

Reviews: