Installation
Problems and corrective measures
5.8
Installation test
The following test plan must be carried out after every installation. If even a single test requirement
is not passed, the vehicle must not be put into operation and it is necessary to return the vehicle to
its original state.
After the Gateway has been installed, the fitter must carry out the following test steps to ensure
operation without interferences and thus a correct installation: The test is performed with the
vehicle’s installation turned on.
– Make sure that the vehicle system does not report any active faults (reading
the instrument panels and the control unit diagnosis).
– Ensure by means of measurement with a CAN reading device that the
source bus is fault-free after connecting it to the MCG.
!
The results of this measurement must be compared to the results of the measurement prior to
installing the Gateway (see chapter "5 Installation" on page 11) and must not differ.
– Connect a reading device to the target bus to ensure that the desired vehicle
data is transmitted from the source bus to the target bus.
If all test items can be confirmed, the MCG was correctly installed and is now ready for use.