16
2.
Delivery and set up
2.2
Transport-lock on milling machines with ball screws
Caution –
prior to machine startup the transport-lock must be removed
How to proceed:
1. With the hand wheel via the Z-axis, drive the milling head a minimal distance up.
2. Remove the wooden support below the milling spindle
3. at least on one side, loosen the transport-lock (1)the bolts (2)
4. the transport-lock (1) must be slidable without resistance
5. if this is not the case, then the milling head must be moved via the hand wheel ofthe Z-axis far enough
away, so that the wire cables under tension and are supportingthe weight.
now the transport-lock (1) is relieved and ca be pulled off.
A ( 1 : 1 )
1
2
Summary of Contents for F1410 LF
Page 41: ...41 7 Fitting and removing the tools 42 6 Spannen und Ausdrücken der Werkzeuge 1 2 3 4 5 ...
Page 98: ...98 16 Drawings and legends 16 12 Spindle Z axis with ball screws 16 12 1 F1410 LF F1410 LF hs ...
Page 126: ...126 16 Drawings and legends 16 22 Support arm for control panel 1 2 3 4 5 6 8 9 5 4 7 9 8 ...