16
OPERATING MANUAL
VERSION 07/2017
ORDER NUMBER DOC 2349369
6.3.1 VENTILATION OF THE SPRAY BOOTH
Operate the device in a spray booth approved for the working materials.
-or-
Operate the device on an appropriate spraying wall with the ventilation (extraction)
switched on.
Observe national and local regulations for the exhaust air speed.
6.4
GROUNDING
A conductive connection (potential equalization cable) must be established between
original bundles and the equipment.
WARNING
Discharge of electrostatically charged components in atmospheres containing
solvents!
Explosion hazard from electrostatic sparks or flames.
Ground all device components.
Ground the work pieces to be coated.
Grounding check
Daily:
Before starting work, carry out a visual inspection to ensure that the system is
grounded.
6.5
LACQUER PREPARATIONS
The viscosity of the lacquer is of great importance. The best spraying results are obtained
with values between 80 and 260 millipascals x sec (mPa∙s).
Please also read the technical data sheet of the lacquer for optimal processing, viscosity
adjustment and intermixing of the product.