Pipe Design
TITANUS
SUPER·SENS
®
4 –
14
Data: 02/09
TSS_04_A-en-e
Procedure
In the following example, a project plan is supposed to fulfil class B re-
quirements without air filters, with 8 apertures and with the additional use
of a condensation separator. The red arrows show the possible project
plans with varying pipe shapes and fan voltages.
Selection
Selection of the corresponding project planning table based on the air filter to be
used (see Chap. 4.2.2 )
Result
1.
The project planning table has been determined
Selection
Selection of the number of aspiration apertures in the project planning table
Result
2.
The achievable sensitivity class for the selected number of apertures has been
determined
Selection
Determinations on the sensitivity necessary to achieve the sensitivity class
Result
3.
Determination of the detector module and sensitivity setting
Selection
Selection of other pipe components ( e.g. steam trap and detonation protection
see Chap. 4.2.2 described components)
Result
4.
The project planning table has been determined
Selection
Pipe length selection
Result
5.
Determination of the pipe shape and necessary fan voltage.