82 Commissioning
WAGO-I/O-SYSTEM 750
750-8207 PFC200 CS 2ETH RS 3G
Manual
Draft version 1.2.1 from 2017-09-13, valid from FW Version 02.06.20(09)
7
Commissioning
7.1
Switching On the Controller
Before switching on the controller ensure that you
•
have properly installed the controller
(see section “Installation”),
•
have connected all required data cables (see section “Connections”) to the
corresponding interfaces and have secured the connectors by their
attached locking screws,
•
have connected the electronics and field-side power supply
(see section “Connections”),
•
have mounted the end module (750-600)
(see Section “Installation”),
•
have performed appropriate potential equalization at your machine/system
(see System Description for 750-xxx) and
•
have performed shielding properly (see System Description for 750-xxx).
To switch on both the controller and the connected I/O modules, switch on your
power supply unit.
Starting of the controller is indicated by a brief green flashing of all LEDs. After a
few seconds the SYS LED will signal successful boot-up of the controller.
The CODESYS 2.3 runtime system or
e!
RUNTIME
is started at the same time.
Once the entire system has been successfully started, the SYS and I/O LEDs
light up green.
If there is an executable IEC 61131-3 program stored and running on the
controller, the RUN LED will light up green.
If no executable program is stored on the controller, or the mode selector switch
is set to STOP, this is likewise indicated by the RUN LED (see Section
“Diagnostics”> … > “Fieldbus/System Indication Elements”).