WAGO WINSTA® 770
Commissioning
39
770-629/130-000 WINSTA® Sunblind Box 4 Channel
Manual
Version 1.1.1, valid from HW/FW version XXXX0201XX
7.4.4
Setting of Bus Failure Monitoring / Voltage Monitoring
Activate/De-activate bus failure monitoring / voltage monitoring using switch 4 of
DIP Module 2.
7.4.4.1
Standard Mode
Make the following settings to de-activate bus failure monitoring / voltage
monitoring:
ON
DIP
1 2 3
4
5 6
Figure 25: Standard Mode
Factory setting
This is the factory setting for the monitoring function.
7.4.4.2
Operation with Bus Failure Monitoring / Voltage Monitoring
Make the following settings to activate bus failure monitoring / voltage
monitoring:
ON
DIP
1 2 3
4
5 6
Figure 26: Operation with bus failure monitoring / voltage monitoring
Voltage Monitoring in Central Operation
At this setting, the switching logic is changed from 2 x make contact elements to
2 x break contact elements. This enables both signals to be monitored. The drives
linked to the system move in the required direction when a contact is opened. If
no voltage is present at either contact the drives move to their top, final position.
Bus Failure Monitoring during Bus Operation
At this setting the bus signal is monitored during bus operation. The drives linked
to the system will move to their top, final position on a continuous bus failure
lasting longer than 3 minutes.