5.0 INSTALLATION AND FIXING
2
FIL.SILOTOP_zero.--.M.A4.0722.EN Issue: A4
07.22
28
5.7 Inspection
Important
When installation is complete, authorized personnel must carry out a general test to ensure that the
safety conditions have been completely satisfied.
The authorized personnel must also check:
- that no tools or other material have been forgotten inside the filter;
- that the fixing screws have been tightened using the prescribed torque;
Before starting up the filter:
- Ensure that the plant in which the filter is installed is compliant to the Directive 2006/42/ EC and to the rel
-
evant directives, the safety standards in force and those specifically applicable;
- Make sure inspection hatches are locked with the supplied bolts inserted in their original position.
- Ensure that the operating conditions were met.
5.8 Start-up
Preliminary checking
After having finished the electrical and pneumatic connections, carry out the following preliminary checks:
- make sure the electronic board is powered and set correctly;
- make sure the air tank pressure is 6 bar;
- make sure all the screws and clamps have been tightened;
- make sure all the elements have been fixed correctly to the seal frame;
- make sure the gaskets are all intact and close the inspection hatch;
- ensure the warning plates are present.
- make sure all pipes connected to the filter, if present, are screwed and properly fitted;